Prevoius Weekly Reports

   Weekly report as on 08.04.2011
    

 

 

SlNo Activities Date  Remarks
1 Joint Inspection with AE,KWA,Angamali 17.3.2011 Estimate is to be received
2 Joint Inspection with DE, BSNL,Angamali 17.3.2011 Estimate is to be received
3 Joint Inspection with Sub Engineer, KSEB,Karukutti 23.3.2011 Estimate is to be received
4 Joint Inspection with AE,Project division,KWA,Aluva 1.4.2011   Estimate  received 
Joint Inspection with AE,KSEB,Angamali  8.4.2011  

 

  1. Site clearance work completed at Puliyanam side.
  2. Site clearance work at N.H. Side  75% completed.
  3. Preliminary arrangements work in progress (Making of Office, Store etc.)
  4. Bridge Centre line marking (except approach portion NH side) completed.
  5. Drainage alignment marking (Puliyanam side) completed.
  6.  Excavation of earth cuttings at Puliyanam side completed and NH side 75% completed
 
Back
 
    
SITE CLEARANCE COMPLETED 8.4.2011

    
    
JOINT INSPECTION WITH RBDCK, KSEB AND SKILLED 8.4.2011

    
    
DRAIN WORK IN PROGRESS 8.4.2011

      
 

 

 

 

 

 

 

 