progress up to 8.4.2011 |
|
SlNo |
Activities |
Date |
Remarks |
1 |
Joint Inspection with Axe and AE,KWA,Pallimukku |
21.2.2011 |
Estimate is to be received |
2 |
Joint Inspection with DE, BSNL,Palarivattom |
23.3.2011 |
DE,informed that there is no BSNL cable to be removed |
|
DE, BSNL,Vytilla |
|
DE,informed that there is no BSNL cable to be removed |
3 |
Joint Inspection with Sub Engineer, KSEB |
23.3.2011 |
DD submitted to Ae KSEB |
4 |
Joint Inspection with BPCL |
24.3.2011 |
|
5 |
Pile Load Test |
23.3.2011 to 27.3.2011 |
Completed on 27.3.2011 6 |
6 |
Joint Inspection with AE,AXE and EE KWA |
2.4.2011 |
|
7 |
Piling started at P15 |
1.4.2011 |
|
8 |
Joint Inspection with AE,KSEB |
11.4.2011 |
for shifting Electrical posts near the level cross |
9 |
Joint Inspection with AE,BSNL |
11.4.2011 |
|
10 |
4 piles completed |
|
|
|
|
Back |
|
SOIL TESTING NEAR RP-2
|
| | |
SOIL TESTING NEAR RP-2.
|
| | |
RIGS AT P15, P14, P12
|
| | |
PROJECT DESCRIPTION BOARD
|
| | |
|
LOCATIONP15-PILE P-2BORING
|
| | |
CHISEL WELDING NEAR P14
|
| | |
BORING P12-PILE P2
|
| | |
|
BORING P12-PILE P2.
|
| | |
BENTONITE TANK P14
|
| | |
SOIL TESTING NEAR RP-2
|
| | |
| |
|
|