Prevoius Weekly Reports

   Weekly report as on 08.04.2011
    
Revised Progress Report For Mulankunnathukavu ROB for the week ending on 08-04-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed    
2 PILE M.C SIDE 36 36 Completed    
3 PILE CAP SHORNUR SIDE 3 3 Completed    
4 PILE CAP  M.C SIDE 12 12 Completed    
5 PIER SHORNUR  SIDE 3 3 Completed    
6 PIER M.C SIDE 12 12 Completed    
7 PIER CAP SHORNUR  SIDE 3 3 Completed    
8 PIER CAP M.C SIDE 12 12 Completed   pedestal concreting completed 6 locations.P13,P12,P11,P10,P9,AP2
9 RE/R WALL SHORNUR  SIDE 100% 9 91% 0 5.00% 2.00% 46.00% 10.00% 116 days PCC laid for 65 square metre shortage  of labour seriously affecting the progress of the work.in the shornur side approach.
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 1.00% 23.00% 5.00% 116 days casting of panels 210no: completed.
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 86 days  
12 BEAM/SLAB M.C SIDE 12 2 10 0 1 0 1 1 146 days concreting of two spans in the M.C side completed.reinforcement work of the girder of the third span P9-P10 over. shuttering of the slab bottom also over..staging work for the 4th span is almost complete.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 53 days  
14 HR/FP/KERB M.C SIDE 100% 3 97% 0 2.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    

 

 

 

Availbility of Men 

           
Date 02-4-'11 4/4/2011 5/4/2011 6/4/2011 7/4/2011 8/4/2011
Nof labours 34 36 36 36 36 38
             
             

 

 

Material Stocking Status

           
  Required Available Remarks      
Fine aggregate {cft} 300 1000        
Cement(bag) 615 1330        
Steel inT 10 13 sufficient material available at the site      
Coarse Aggreagate (cft) 600 1000        

 

 

Utility shifting  
Utilities to be shifted   Remarks
BSNL  hindrance talked to the BSNL in charge of the locality.agreement made to re-route the cable.
KSEB already shifted  
KWA  hindrance given the letter to the AE  and AXE of the water authority ,thrissur,to visit the site and take the estimate of the rerouting cost as soon as posssible.the hindrance is in the west side of canal.The water authority has  inspected the site to take the estimate and will send the details to RBDCK
Others road diversion work    IN PROGRESS.only bitumenous macadum layer is left to be done.  
  The canal deviation work to be commenced soon after clearing of KWA line and BSNL cable.  
 
Back
 
    
REINFORCEMENT WORK FOR SPAN P9-P10 - 04.04.2011

    
    
SHUTTERING WORK FOR SPAN P9-P10 - 05.04.2011

    
    
REINFORCEMENT WORK SPAN P9-P10 - 05.04.2011

    
    
PCC FOR RC WALL AT SHORNUR SIDE - 05.04.2011

    
 
    
STAGING AND SHUTTERING SPAN P9-P10 - 08.04.2011

      
 

 

 

 

 

 

 

 