Prevoius Weekly Reports

   progress up to 1.4.2011
    

 

SlNo Activities Date  Remarks
1 Joint Inspection with AE,KWA,Angamali 17.3.2011 Estimate is to be received
2 Joint Inspection with DE, BSNL,Angamali 17.3.2011 Estimate is to be received
3 Joint Inspection with Sub Engineer, KSEB,Karukutti 23.3.2011 Estimate is to be received
4 Joint Inspection with AE,Project division,KWA,Aluva 1.4.2011   
       

 

  1. Site clearance work completed at Puliyanam side.
  2. Site clearance work at N.H. Side  75% completed.
  3. Preliminary arrangements work in progress (Making of Office, Store etc.)
  4. Bridge Centre line marking (except approach portion NH side) completed.
  5. Drainage, alignment marking (Puliyanam side) completed.
  6.  Excavation of earth cuttings at Puliyanam side completed and NH side 75% completed
 