SlNo |
Activities |
Date |
Remarks |
1 |
Joint Inspection with AE,KWA,Angamali |
17.3.2011 |
Estimate is to be received |
2 |
Joint Inspection with DE, BSNL,Angamali |
17.3.2011 |
Estimate is to be received |
3 |
Joint Inspection with Sub Engineer, KSEB,Karukutti |
23.3.2011 |
Estimate is to be received |
4 |
Joint Inspection with AE,Project division,KWA,Aluva |
1.4.2011 |
|
|
|
|
|
-
Site clearance work completed at Puliyanam side.
-
Site clearance work at N.H. Side 75% completed.
-
Preliminary arrangements work in progress (Making of Office, Store etc.)
-
Bridge Centre line marking (except approach portion NH side) completed.
-
Drainage, alignment marking (Puliyanam side) completed.
-
Excavation of earth cuttings at Puliyanam side completed and NH side 75% completed
|