Prevoius Weekly Reports

   progress up to 1.4.2011
    

 

SlNo Activities Date  Remarks
1 Joint Inspection with Axe and AE,KWA,Pallimukku 21.2.2011 Estimate is to be received
2 Joint Inspection with DE, BSNL,Palarivattom 23.3.2011 DE,informed that there is no BSNL cable to be  removed
   DE, BSNL,Vytilla   DE,informed that there is no BSNL cable to be  removed
3 Joint Inspection with Sub Engineer, KSEB 23.3.2011 DD submitted to Ae KSEB
4 Joint Inspection with BPCL

24.3.2011

 

 
5 Pile Load Test  23.3.2011 to 27.3.2011 Completed on 27.3.2011  6
  Joint Inspection with AE,AXE and EE KWA 2.4.2011  
  Piling started at P15 1.4.2011  
 