SlNo |
Activities |
Date |
Remarks |
1 |
Joint Inspection with Axe and AE,KWA,Pallimukku |
21.2.2011 |
Estimate is to be received |
2 |
Joint Inspection with DE, BSNL,Palarivattom |
23.3.2011 |
DE,informed that there is no BSNL cable to be removed |
|
DE, BSNL,Vytilla |
|
DE,informed that there is no BSNL cable to be removed |
3 |
Joint Inspection with Sub Engineer, KSEB |
23.3.2011 |
DD submitted to Ae KSEB |
4 |
Joint Inspection with BPCL |
24.3.2011
|
|
5 |
Pile Load Test |
23.3.2011 to 27.3.2011 |
Completed on 27.3.2011 6 |
|
Joint Inspection with AE,AXE and EE KWA |
2.4.2011 |
|
|
Piling started at P15 |
1.4.2011 |
|
|