SlNo |
Activity -Description |
Total Quantity |
Cumulative progress up to this week(1) |
Balance work(2) |
Cumulative delay in weeks after Spplagmnt(3) |
Work planned during the week(4) |
Actual work done during the last week(5) |
Short fall in the last week (6) |
Work Planned for next week (7) |
No of days remaing for completion as per the weekly plan(8) |
Remarks |
1 |
Re wall towards NH side |
100% |
26% |
78 |
57 |
5 |
4 |
1 |
2 |
53 days |
. |
3 |
Approach |
5 No |
4 |
1 |
28 |
- |
- |
- |
- |
|
|
Span |
4 |
Pier cap |
4no |
0 |
4 |
27 |
0 |
0 |
0 |
1 |
53 |
Staging works and shuttering works for the P2 location planned for the next week. concreting of the piercap P2 to be done next week |
5 |
Pile (Rly)pulikakadavu side |
9 |
4 |
5 |
47 |
0 |
0 |
0 |
0 |
23 |
Caution is required for balance piling work |
|
6 |
Pile (Rly)Nh side |
9 |
4 |
5 |
47 |
0 |
0 |
0 |
0 |
23 |
Caution is required for balance piling work |
6 |
Piers (Rly) |
4No |
1 |
3 |
38 |
0 |
0 |
0 |
0 |
|
|
9 |
R0AD WORK |
100% |
60%WBM completed. |
0 |
|
15 |
30% |
|
30% |
53 days |
WBM 2ndtlayer completed. |
|
10 |
Staging work for P3-P2 span |
100% |
35 |
75 |
|
5 |
5 |
|
10 |
83 days |
100 days |
11 |
Excavation at P7 |
100% |
95 |
5 |
|
|
|
|
5 |
0 |
|
12 |
Pile Load Test at P1 In the NH side |
100% |
|
|
|
|
|
|
|
|
Arrangement for pile load test in progress.joint inspection of railways and rbdck |
Kerb and hand rail towards Pulikkakadavu side completed |