Prevoius Weekly Reports

   weekly progress 1.4.2011
    

 

SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week(1) Balance  work(2) Cumulative delay in weeks after  Spplagmnt(3) Work  planned  during the week(4) Actual work done during the last week(5) Short fall in the last week (6) Work  Planned for next week (7) No of days remaing for completion as per the weekly plan(8) Remarks 
1 Re wall towards NH side  100% 26% 78 57 5 4 1 2  53 days  .
3 Approach  5 No  4 1 28     
 Span 
4 Pier cap  4no  0 4 27  0   0   0   1   53  Staging works and shuttering works for the P2 location planned for the next week. concreting of the piercap P2 to be done next week
5 Pile (Rly)pulikakadavu side  9 4 5 47  0  0   0    0  23 Caution is required for balance piling work
  
6 Pile (Rly)Nh side 9 4 5 47 0 0 0 0 23 Caution is required for balance piling work 
6 Piers (Rly) 4No  1 3 38  0   0   0   0     
9 R0AD WORK 100% 60%WBM completed. 0     15   30%      30% 53 days  WBM  2ndtlayer completed. 
 
10 Staging work for P3-P2 span 100% 35 75   5 5   10 83 days 100 days
11 Excavation at P7  100% 95 5         5 0  
12 Pile Load Test at P1 In the NH side 100%                 Arrangement for pile load test in progress.joint  inspection of railways and rbdck 
Kerb and hand rail towards Pulikkakadavu side completed 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate(m3)

25

30

Remarks

 

Fine Aggreagate(m3)

 4

 6

 .

 

Cement(bag)

 20

 30

 

 

Steel(MT)

 2

 9

 

 

 

 

 

 

  

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 Nil

 

 

 

KSEB

 Nil

 

 

 

KWA

 Nil

 .

 

 

Others

Nil

 

 

  

 
Back
 
    
RE WALL WORK AT THE NH SIDE 29.3.2011

    
    
WORK OF PIER CAP 31.3.2011

    
    
PILE LOAD TEST ARRANGEMENT AT P1 30.3.2011

    
    
RE WALL WORK AT THE NH SIDE 28.3.2011

    
 
    
REINFORCEMENT WORK OF PIER CAP AT P2 26.3.2011

    
    
JOINT INSPECTION WITH RBDCK,RAILWAYS,KITCO AND CVCC AT P1 IN THE NH SIDE 1.4.2011

      
 

 

 

 

 

 

 

 