Revised Progress Report For Mulankunnathukavu ROB for the week ending on 01-04-2011 |
|
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
Completed |
|
|
2 |
PILE M.C SIDE |
36 |
36 |
Completed |
|
|
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
Completed |
|
|
4 |
PILE CAP M.C SIDE |
12 |
12 |
Completed |
|
|
5 |
PIER SHORNUR SIDE |
3 |
3 |
Completed |
|
|
6 |
PIER M.C SIDE |
12 |
12 |
Completed |
|
|
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
Completed |
|
|
8 |
PIER CAP M.C SIDE |
12 |
12 |
Completed |
|
pedestal concreting completed 6 locations.P13,P12,P11,P10,P9,AP2 |
9 |
RE/R WALL SHORNUR SIDE |
100% |
7 |
93% |
0 |
10.00% |
2.00% |
43.00% |
5.00% |
123 days |
PCC laid for 20 metres acute shortage of labour seriously affecting the progress of the work.in the shornur side approach. |
10 |
RE/R WALL M.C SIDE |
100% |
8 |
92% |
0 |
10.00% |
0.00% |
19.00% |
5.00% |
123 days |
casting of panels 190no: completed. |
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
0 |
3 |
0 |
0 |
0 |
0 |
0* |
93 days |
|
12 |
BEAM/SLAB M.C SIDE |
12 |
2 |
10 |
0 |
1 |
0 |
1 |
1 |
153 days |
concreting of two spans in the M.C side completed.staging work of the third span P9-P10 over.reinforcement works for the third span to be started soon.staging work for the 4th span to be started very soon.deshuttering works for the 2nd span in progress. |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
60 days |
|
14 |
HR/FP/KERB M.C SIDE |
100% |
3 |
97% |
0 |
2.00% |
3.00% |
0.00% |
2.00% |
|
kerb work in progress.kerb work of AP2-P13 completed |
15 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|