   Weekly report as on 01.04.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 01-04-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed    
2 PILE M.C SIDE 36 36 Completed    
3 PILE CAP SHORNUR SIDE 3 3 Completed    
4 PILE CAP  M.C SIDE 12 12 Completed    
5 PIER SHORNUR  SIDE 3 3 Completed    
6 PIER M.C SIDE 12 12 Completed    
7 PIER CAP SHORNUR  SIDE 3 3 Completed    
8 PIER CAP M.C SIDE 12 12 Completed   pedestal concreting completed 6 locations.P13,P12,P11,P10,P9,AP2
9 RE/R WALL SHORNUR  SIDE 100% 7 93% 0 10.00% 2.00% 43.00% 5.00% 123 days PCC laid for 20 metres acute shortage of labour seriously affecting the progress of the work.in the shornur side approach.
10 RE/R WALL M.C SIDE 100% 8 92% 0 10.00% 0.00% 19.00% 5.00% 123 days casting of panels 190no: completed.
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 93 days  
12 BEAM/SLAB M.C SIDE 12 2 10 0 1 0 1 1 153 days concreting of two spans in the M.C side completed.staging work of the third span P9-P10 over.reinforcement works for the third span to be started soon.staging work for the 4th span to be started very soon.deshuttering works for the 2nd span in progress.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 60 days  
14 HR/FP/KERB M.C SIDE 100% 3 97% 0 2.00% 3.00% 0.00% 2.00%   kerb work in progress.kerb work of AP2-P13 completed
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
                       

 

Availbility of Men           
Date 26-3-'11 28-3-2011 29-3-2011 30-3-2011 31-3-2011 1/4/2011
Nof labours 26 34 34 27 28 31
             
Material Stocking Status          
  Required Available Remarks      
Fine aggregate {cft} 300 1000        
Cement(bag) 100 1350        
Steel inT 10 13 sufficient material available at the site      
Coarse Aggreagate (cft) 600 1000        

 

Utility shifting    
Utilities to be shifted   Remarks
BSNL  hindrance talked to the BSNL in charge of the locality.agreement made to re-route the cable.
KSEB already shifted  
KWA  hindrance given the letter to the AE  and AXE of the water authority ,thrissur,to visit the site and take the estimate of the rerouting as soon as posssible.the hindrance is in the west side of canal .The water authority has agreed to visit the site the next week.
Others road diversion work    IN PROGRESS.only bitumenous macadum layer is left to be done.  
  The canal deviation work to be commenced soon after clearing of KWA line and BSNL cable.   
 
Back
 
    
STAGING WORKS OF THE THIRD SPAN, P9-P10 - 26.03.2011

    
    
PCC IN THE APPROACH SIDE OF THE SHORNUR SIDE - 28.03.2011

    
    
KERB CONCRETING - 29.03.2011

    
    
STAGING WORK OF THIRD SPAN - P9-P10 - 30.03.2011

    
 
    
DESHUTTERING OF THE SIDES OF THE BEAM AND SLAB BOTTOM OF THE SPAN AP2-P13 - 31.03.2011

    
    
KERB CONCRETING - 01.04.2011

      
 

 

 

 

 

 

 

 