Prevoius Weekly Reports

   01.04.2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress uptolast week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

RE/R WALL PALAKKAD  SIDE

100%

40

60

0

0.00%

5.00%

0.00%

5.00%

 

2

RE/R WALL MOYAN SCHOOL SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

3

BEAM/SLAB  Staging  PALAKKAD  SIDE

2

0

2

0

0

0

0

0

 

4

BEAM/SLAB  Bar bending and Fixing PALAKKAD  SIDE

2

0

2

0

0

0

0

0

 

5

BEAM/SLAB  Bar Shuttering And Concreting PALAKKAD  SIDE

2

0

2

0

0

0

0

0

 

6

BEAM/SLAB  Staging MOYAN SCHOOL SIDE

4

2

1

0

0

1

0

1

P7-P8  

7

BEAM/SLAB  Bar bending And Fixing MOYAN SCHOOL SIDE

4

2

1

0

0

1

0

1

 P6-P7in Progress

8

BEAM/SLAB  Shuttering and Concreting MOYAN SCHOOL SIDE

4

2

2

0

0

1

0

0

 P6-P7in Progress

9

BEAM/SLAB RAILWAY SPAN

7

0

7

0

0

0

1

0

 

10

HR/FP/KERB CALICUT  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

11

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

12

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

13

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: Progress review done based on the revised Program (rev-01)

 

 

 

      

Availbility of Men

 

 

 

 

 

Date

26-3-'11

28-3-2011

29-3-2011

30-3-2011

31-3-2011

04-01-2011

Nof labours

45

45

45

45

45

45

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

 

 

 

Required

Available

Remarks

 

 

 

Fine aggregate {m³}

 

 

 

 

 

 

Cement(bag)

300

674

 

 

 

 

Steel inT

6

85

 

 

 

 

Coarse Aggreagate (m3)

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

 

Utilities to be shifted

 

Remarks

 

 

 

 

BSNL

Nil

 

 

 

 

 

KSEB

Nil

 

 

 

 

 

KWA

 

progress

 

 

 

 

Others

 

 

 

 

 

 

          

 
Back
 
    
STAGING OF P6-P7(01.04.2011)

    
    
RT. WALL BARBENDING MOYENS SIDE (31.03.2011)

    
    
STAGING WORKS OF P6-P7(30.03.2011)

    
    
RET. WALL SHUTTERING (30.03.2011)

    
 
    
EXCAVATION FOR RET. WALL NEAR P1 (30.03.2011)

    
    
RAFT CONCRETING (29.03.2011)

      
 

 

 

 

 

 

 

 