Prevoius Weekly Reports
|
weekly progress 25.3.2011 |
|
SlNo |
Activities |
Date |
Remarks |
1 |
Joint Inspection with Axe and AE,KWA,Pallimukku |
21.2.2011 |
Estimate is to be received |
2 |
Joint Inspection with DE, BSNL,Palarivattom |
23.3.2011 |
DE,informed that there is no BSNL cable to be removed |
|
DE, BSNL,Vytilla |
|
DE,informed that there is no BSNL cable to be removed |
3 |
Joint Inspection with Sub Engineer, KSEB |
23.3.2011 |
Action taken for remitting shifting charge |
4 |
Joint Inspection with BPCL |
24.3.2011
|
|
5 |
Pile Load Test |
23.3.2011 to 27.3.2011 |
Completed on 27.3.2011 |
|
|
Back |
|
PILE LOAD TEST ARRANGEMENT 26.3.2011
|
| | |
PILE LOAD TEST 26.3.2011
|
| | |
JOINT INSPECTION WITH BPCL ,CVCC,KITCO AND RBDCK 24.3.2011(2)
|
| | |
JOINT INSPECTION WITH BPCL ,CVCC ,KITCO AND RBDCK 24.3.2011
|
| | |
|
RAILWAY PIER RP2
|
| | |
BPCL PIPES ALONG THE ALIGNMENT(8.3.2011)
|
| | |
JOINT INSPECTION WITH KITCO ,CVCC AND RBDCK 8.3.2011
|
| | |
| |
|
|