   progress as on 25.3.2011
    

 

SlNo Activities Date  Remarks
1 Joint Inspection with AE,KWA,Angamali 17.3.2011 Estimate is to be received
2 Joint Inspection with DE, BSNL,Angamali 17.3.2011 Estimate is to be received
3 Joint Inspection with Sub Engineer, KSEB,Karukutti 23.3.2011 Estimate is to be received
4 Joint Inspection with AE,Project division,KWA,Aluva yet to be done   Comunication sent to EE,Project Division,KWA,Aluva

 

  1. Site clearance work completed at Puliyanam side.
  2. Site clearance work at N.H. Side  75% completed.
  3. Preliminary arrangements work in progress (Making of Office, Store etc.)
  4. Bridge Centre line marking (except approach portion NH side) completed.
  5. Drainage, alignment marking (Puliyanam side) completed.
  6. Excavation of earth cuttings at Puliyanam side completed and NH side 75% completed. 

 

 

 
Back
 
    
SITE CLEARANCE WORK 8.3.2011

    
    
PROJECT SITE

      
 

 

 

 

 

 

 

 