   weekly progress 25.3.2011
    

 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

Remarks

1

Re wall towards NH side

100%

22%

78

23

6

4

2

5

 60 days

.

2

RE wall towards Pulikkakadavuside

100%

100

0

42

0

0

0

0

 0

 

3

Approach

 Span

5 No

4

1

23

-

-

-

-

 

 

4

Pier cap

4no

0

4

28

 0

 0

 0

 0

 60

 

5

Pile (Rly)pulikakadavuside

9

4

 

5

49

 0

 0

30

Caution awaited

6

Pile (Rly)Nhside

9

4

5

48

0

0

0

0

30

Caution awaited

6

Piers (Rly)

 

4No

1

3

40

 0.5

 0.5

 0

 0

 

Caution awaited

9

R0AD WORK

100%

30%WBM completed.

 

0

 

 

 

 

 15%WBM planned

60 days

1st layer completed

10

Staging work for P3-P2 span

100%

30

70

 

 

 

 

5

90 days

 

11

Excavation at P7

100%

95

5

 

 

 

 

5

0

 

12

Pile Load Test at P1 In the NH side

100%

 

 

 

 

 

 

 

 

25% Materials for kentledgewas brought to the site.

 

 

Kerband hand rail towards Pulikkakadavuside completed 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

18

27

Remarks

 

Fine Aggreagate(m3)

 3

 4.5

 .

 

Cement(bag)

 10

 38

 

 

Steel(MT)

 2

 9

 

 

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 No hindrance

 

 

 

KSEB

 KSEBoverhead line shifted on 23-3-2011

 

 

 

KWA

 No hindrance

 .

 

 

Others

 asianetcable at the approachportion. Removed.

No hindrance

 i

 

  

 

Date 19.3.2011 21.3.2011 22.3.2011 23.3.2011 24.3.2011
 No of Labour s 28 30 28 32 32 
 
Back
 
    
WBM WORK IN PROGRESS 25.3.2011

    
    
RE WALL IN THE NH SIDE 24.3.2011

    
    
PIER CAP AT P2- 2ND LIFT CONCRETING 24.3.2011.JPG

    
    
EARTH WORK EXCAVATION 23.3.2011

    
 
    
EARTH EXCAVATION IN PROGRESS 22.3.2011

    
    
PAINTING BENEATH THE GIRDER 23.3.2011

    
    
WBM WORK IN PROGRESS (PULIKAKADAVU SIDE) 19.3.2011

    
 
    
WBM WORK IN PROGRESS AT PULIKAKADAVU SIDE 19.3.2011

      
 

 

 

 

 

 

 

 