Prevoius Weekly Reports
|
17.7.2010 |
| |
ROB at Athani
|
RE wall works Medical College side |
Completed |
Restarted on 12.4.10 |
|
PCC for friction slab |
Completed |
|
|
Friction slab concreting |
Completed |
|
|
Hand rail for RE wall |
Completed |
|
|
Road work |
Completed |
|
|
Toll Booth - Plastering work |
In progress |
|
|
Painting |
In progress |
|
|
| |
| Back |
| |
No images are uploaded for this Weekly Reports
|
| |
|