Prevoius Weekly Reports

   Weekly report as on 25.03.2011
    

 

Progress Report For Kainatty ROB for the week ending on 25-03-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 3 3 2 2 0 3 3    
4 PILE CAP  NADAPURAM SIDE 9 5 4 4 4 1 3 3    
5 PIER KAINATTY  SIDE 6 3 3 4 3 0 3 3    
6 PIER NADAPURAM SIDE 9 3.5 5.5 4 4 0 5.5 4    
7 PIER CAP KAINATTY  SIDE 6 0 6 6 4 1 5 4    
8 PIER CAP NADAPURAM SIDE 9 0 9 8 4 0 8 4    
9 Staging AP1-P1 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 RE/R WALL NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
12 BEAM/SLAB  Staging Kainatty side 6 0 6 0 1 0.05 0 1    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 0 6 0 1 0 0 1    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 0 6 0 0 0 0 1    
15 BEAM/SLAB  Staging Nadapuram side 9 0 9 0 0 0 0 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 0 9 0 0 0 0 1    
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 0 9 1 0 0 0 0    
18 BEAM/SLAB KAINATTY  SIDE 6 0 6 0 0 0 0 0    
19 BEAM/SLAB NADAPURAM SIDE 9 0 9 0 0 0 0 0    
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
                       
  Note: Progress review done based on the revised Program (rev-01)        
                       
                       
 

 

Availbility of Men 

                 
  Date   19-03-11 20-03-11 21-03-11 22-03-11 23-03-11 24-03-11 25-03-11    
  Nof labours   30 30 30 30 30 30 30    
                       
 

 

 

Material Stocking Status

               
    Required Available Remarks              
  Fine Aggreagate(m3) 25 15                
  Cement(bag) 1000 800                
  Steel(MT) 30 23                
  Coarse Aggreagate (m3) 30 20                
                       
 

 

 

Utility shifting

                 
  Utilities to be shifted Status Remarks                
  BSNL shifted                  
  KSEB shifted                  
  KWA to be shifted                  
  Others                    

 

 
Back
 
    
EXCAVATION OF AP2 - 17.03.2011

    
    
TANK FOR CUBES - 19.03.2011

    
    
SLABS FOR STAGING - 19.03.2011

    
    
CHIPPING OF P13 - 21.03.2011

    
 
    
PIERCAPS AP1 - 23.03.2011

    
    
OFC AT AP2 LOCATION - 24.03.2011

      
 

 

 

 

 

 

 

 