   Weekly report as on 25.03.2011
    

 

Progress Report For Payyannur ROB for the week ending on 25-03-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE THRIKKARIPUR  SIDE 33 33 0 0 0 0 0 0    
2 PILE EZHIMALA SIDE 27 27 0 0 0 0 0 0    
3 PILE PAYYANNUR SIDE 27 27 0 0 0 0 0 0    
4 PILE CAP THRIKKARIPUR  SIDE 11 11 0 0 0 0 0 0    
5 PILE CAP EZHIMALA SIDE 9 9 0 0 0 0 0 0    
6 PILE CAP PAYYANNUR SIDE 9 9 0 0 0 0 0 0    
9 PIER THRIKKARIPUR  SIDE 11 10.5 0.5 0 0.5 0.2 0.2 0.2    
8 PIER EZHIMALA SIDE 9 9 0 0 0 0 0 0    
9 PIER PAYYANNUR SIDE 9 9 0 0 0 0 0 0    
10 PIER CAP THRIKKARIPUR  SIDE 11 8 3 3 3 0 3 3    
11 PIER CAP EZHIMALA SIDE 9 3 6 6 4 0 6 4    
12 PIER CAP PAYYANNUR SIDE 9 4 5 7 5 2 5 5    
16 RE/R WALL THRIKKARIPUR  SIDE 100% 35% 65% 0 0.00% 0.00% 0.00% 0.00%    
17 RE/R WALL EZHIMALA SIDE 100% 25% 75% 0 0.00% 0.00% 0.00% 0.00%    
18 RE/R WALL PAYYANNUR SIDE 100% 0 100% 0 0.00% 0.00% 100.00% 0.00%    
19 BEAM/SLAB  Staging Thrikkaripur side 9 1 8 0 1 1 3 1    
20 BEAM/SLAB  Bar bending and Fixing Thrikkaripur side  9 0 9 0 1 2 3 1    
21 BEAM/SLAB  Shuttering  and Concreting  Thrikkaripur side 9 0 9 0 0 0 3 1    
22 BEAM/SLAB  Staging Ezhimala side 8 0 8 0 0 0 0 1    
23 BEAM/SLAB  Bar bending and Fixing Ezhimala side 8 0 8 0 0 0 0 2    
24 BEAM/SLAB  Shuttering  and Concreting  Ezhimala side 8 0 8 0 0 0 0 1    
25 BEAM/SLAB  Staging Payyanur side 9 0 9 0 0 1 0 1    
26 BEAM/SLAB  Bar bending and Fixing Payyanur side 9 0 9 0 0 0.7 0 1    
27 BEAM/SLAB  Shuttering  and Concreting Payyanur side 9 0 9 0 0 0 0      
28 BEAM/SLAB THRIKKARIPUR  SIDE 10 1 9 0 0 0 0 0    
29 BEAM/SLAB EZHIMALA SIDE 8 0 8 0 0 0 0 0    
30 BEAM/SLAB PAYYANNUR SIDE 9 0 9 0 0 0 0 0    
31 HR/FP/KERB THRIKKARIPUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
32 HR/FP/KERB EZHIMALA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
33 HR/FP/KERB PAYYANNUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
34 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
                       
  Note: Progress review done based on the revised Program (rev-01)        
                       
                       
 

 

Availbility of Men 

                 
  Date   19-03-11 20-03-11 21-03-11 22-03-11 23-03-11 24-03-11 25-03-11    
  Nof labours   52 52 52 52 60 60 60    
                       
 

 

Material Stocking Status

               
    Required Available Remarks              
  Coarse Aggreagate (m3)                    
  Fine Aggreagate(m3)                    
  Cement(bag) 500 1100                
  Steel(MT) 7 300                
                       
                       

 

 
Back
 
    
SHUTTERING P1_P2 - 23.03.2011

    
    
P17_P18 STAGGING AND REINFORCEMENT 23.03.2011

    
    
P3_P4 GIRDER REINFORCEMENT - 23.03.2011

    
    
P1_P2 GIRDER REINFORCEMENT - 23.03.2011

    
 
    
ELECTRICPOST SHIFTED EZHIMALA SIDE - 23.03.2011

    
    
EZHIMALA SIDE - 22.03.2011

    
    
CONCRETE SETUP FOR P6 - 22.03.2011

    
 
 
 

 

 

 

 

 

 

 