   Weekly report as on 25.03.2011
    
Revised Progress Report For Mulankunnathukavu ROB for the week ending on 25-03-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed
2 PILE M.C SIDE 36 36 Completed
3 PILE CAP SHORNUR SIDE 3 3 Completed
4 PILE CAP  M.C SIDE 12 12 Completed
5 PIER SHORNUR  SIDE 3 3 Completed
6 PIER M.C SIDE 12 12 Completed
7 PIER CAP SHORNUR  SIDE 3 3 Completed
8 PIER CAP M.C SIDE 12 12 0 0 0 0 0 pedestal concreting completed 6 locations.P13,P12,P11,P10,P9,AP2
9 RE/R WALL SHORNUR  SIDE 100% 5 95% 0 15.00% 2.00% 30.00% PCC laid for 10 metres.
10 RE/R WALL M.C SIDE 100% 8 92% 0 7.00% 1.00% 9.00% casting of panels 190no: completed.
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 1 11 0 1 1 0 concreting of AP2-P13 span in progress.staging works of the span P9-P10  will start very soon.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 1 99% 0 0.00% 1.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00%   

 

 

 

Availbility of Men             
Date 19-3-'11 21-3-2011 22-3-2011 23-3-2011 24-3-2011 25-3-2011
Nof labours 23 23 23 23 23 50 

 

 

 

Material Stocking Status            
  Required Available Remarks      
Fine aggregate {cft} 1500 2500        
Cement(bag) 700 1000        
Steel inT 12.35 13 sufficient material available at the site      
Coarse Aggreagate (cft) 5000 8000        

 

 

 

Utility shifting    
Utilities to be shifted   Remarks
BSNL  hindrance talked to the BSNL in charge of the locality.agreement made to re-route the cable.
KSEB already shifted  
KWA  hindrance given the letter to the AE  and AXE of the water authority ,thrissur,to visit the site and take the estimate of the rerouting cost as soon as posssible.the hindrance is in the west side of canal
Others road diversion work    IN PROGRESS.only bitumenous macadum layer is left to be done.  
  The canal deviation work to be commenced soon after clearing of KWA line and BSNL cable. 

 

 
Back
 
    
SHUTTERING WORK OF THE DECK SLAB AP2 - P11 - 19.03.2011

    
    
REINFORCEMENT WORK OF THE DECK SLAB AP2-P13 - 21.03.2011

    
    
REINFORCEMENT WORK OF THE DECK SLAB - 22.03.2011

    
    
CONCRETING OF KERB OF SLAB P11-P12 AND DESHUTTERING - 23.03.2011

    
 
    
CONCRETING OF PANEL - 24.03.2011

    
    
CONCRETING OF DECK SLAB AP2-P13 -25.03.2011

      
 

 

 

 

 

 

 

 