Revised Progress Report For Mulankunnathukavu ROB for the week ending on 25-03-2011 |
|
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
Completed |
2 |
PILE M.C SIDE |
36 |
36 |
Completed |
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
Completed |
4 |
PILE CAP M.C SIDE |
12 |
12 |
Completed |
5 |
PIER SHORNUR SIDE |
3 |
3 |
Completed |
6 |
PIER M.C SIDE |
12 |
12 |
Completed |
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
Completed |
8 |
PIER CAP M.C SIDE |
12 |
12 |
0 |
0 |
0 |
0 |
0 |
pedestal concreting completed 6 locations.P13,P12,P11,P10,P9,AP2 |
9 |
RE/R WALL SHORNUR SIDE |
100% |
5 |
95% |
0 |
15.00% |
2.00% |
30.00% |
PCC laid for 10 metres. |
10 |
RE/R WALL M.C SIDE |
100% |
8 |
92% |
0 |
7.00% |
1.00% |
9.00% |
casting of panels 190no: completed. |
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
0 |
3 |
0 |
0 |
0 |
0 |
|
12 |
BEAM/SLAB M.C SIDE |
12 |
1 |
11 |
0 |
1 |
1 |
0 |
concreting of AP2-P13 span in progress.staging works of the span P9-P10 will start very soon. |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
|
14 |
HR/FP/KERB M.C SIDE |
100% |
1 |
99% |
0 |
0.00% |
1.00% |
0.00% |
|
15 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
|