SlNo |
Activity -Description |
Total Quantity |
Cumulative progress up to this week(1) |
Balance work(2) |
Cumulative delay in weeks afterSpplagmnt (3) |
Work planned during the week(4) |
Actual work done during the last week(5) |
Short fall in the last week (6) |
Work Planned for next week (7) |
No of days remaining for completion as per the weekly plan(8) |
Remarks |
1 |
Re wall towards NH side |
100% |
19% |
81% |
22 |
5 |
4 |
1 |
6 |
|
KSEB overhead line to be shifted |
2 |
RE wall towards Pulikkakadavuside |
100% |
100 |
0 |
41 |
0 |
0 |
0 |
0 |
|
|
3 |
Approach |
5 No |
4 |
1 |
22 |
- |
- |
- |
- |
|
|
Span |
4 |
Railwayspan |
3No |
0 |
0 |
28 |
|
|
|
|
|
|
5 |
Pile (Rly)pulikakadavu side |
9 |
4 |
5 |
48 |
0 |
0 |
0 |
0 |
|
Caution awaited from railways |
6 |
Pile (Rly)Nh side |
9 |
4 |
5 |
|
0 |
0 |
0 |
0 |
|
Caution awaited from railways |
6 |
Piers (Rly) |
4No |
0.5 |
3.5 |
39 |
|
|
|
0.5 |
|
|
9 |
Road work |
100% |
0 |
0 |
|
|
|
|
|
30 |
Sectioning work at the pulikkakadavu side in progress. |
10 |
Staging work for P3-P2 span |
100% |
25% |
75% |
|
|
|
|
5 |
15 |
|
11 |
Excavation at P7 and P1 in the NH side |
100% |
65% |
35% |
|
|
|
|
25 |
10 |
|
12 |
Pile Load Test at P1 In the NH side |
100% |
|
|
|
|
|
|
|
15 |
Approval pending from Railways;25% Materials for kentle ledgewas brought to the site. |