   weekly progress 18.3.2011
    

 

SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week(1) Balance  work(2) Cumulative delay in weeks afterSpplagmnt (3) Work  planned  during the week(4) Actual work done during the last week(5) Short fall in the last week (6)  Work  Planned for next week (7) No of days remaining for completion as per the weekly plan(8) Remarks 
1 Re wall towards NH side  100% 19% 81% 22 5 4 1 6   KSEB overhead line to be shifted
2 RE wall towards Pulikkakadavuside  100% 100 0 41 0 0 0 0    
3 Approach  5 No  4 1 22     
 Span 
4 Railwayspan 3No  0 0 28                 
5 Pile (Rly)pulikakadavu side  9 4 5 48  0  0   0    0    Caution  awaited from railways
6 Pile (Rly)Nh side 9 4 5   0 0 0 0   Caution awaited from railways
6 Piers (Rly)  4No  0.5 3.5 39           0.5     
9 Road work  100% 0 0                30 Sectioning work at the pulikkakadavu side in progress.
10 Staging work for P3-P2 span 100% 25% 75%         5 15  
11 Excavation at P7  and P1 in the NH side 100% 65% 35%         25 10  
12 Pile Load Test at P1 In the NH side 100%               15 Approval pending from Railways;25% Materials for kentle ledgewas brought to the site.  

 

Material Stocking Status    
Coarse Aggreagate (m3) 20 25
Fine Aggreagate(m3)  3   5 
Cement(bag)  5   26 
Steel(MT)  3   10 
      

 

Utility shifting      
Utilities to be shifted Status Remarks
BSNL Utilities removed  
KSEB Obstruction at the NH side.   Materials  brought  to the site for shifting. AE,KESB agreed to arrange the work on 19.3.2011
KWA Utilities removed  
Others  asianet cable at the approach portion.   informed  to the concerned authorities  

 

DATE 12-3-2011 14-3-2011 15-3-2011 16-3-2011 17-3-2011 18-3-2011
Labours (No) 30 27 25 27 27 29 
 
Back
 
    
SECTIONING FOR ROAD WORKS AT PULIKAKKADAVU SIDE 14.3.2011

    
    
FIRST LIFT OF PIER CONCRETING AT P2 11.3.2011

    
    
RE WALL WORK IN THE NH SIDE 12.3.2011

    
    
RE WALL IN THE NH SIDE 14.3.2011

    
 
    
RE WALL IN THE NH SIDE 15.3.2011

    
    
REINFORCEMENT FOR 2ND LIFT OF PIER P2 16.3.2011

    
    
RE WALL IN THE NH SIDE 17.3.2011

    
 
    
RE WALL IN THE NH SIDE 18.3.2011

    
    
EXCAVATION IN PROGRESS AT P7 18.3.2011

      
 

 

 

 

 

 

 

 