Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8051542
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   18.03.2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PIER CAP PALAKKAD SIDE

1

0

1

1

1

1

0

0

 

2

PIER CAP MOYAN SCHOOL SIDE

3

3

0

1

1

1

0

0

 

3

RE/R WALL PALAKKAD  SIDE

100%

40

60

0

0.00%

5.00%

0.00%

5.00%

 

4

RE/R WALL MOYAN SCHOOL SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

5

BEAM/SLAB  Staging  PALAKKAD  SIDE

2

0

2

0

0

0

0

0

 

6

BEAM/SLAB  Bar bending and Fixing PALAKKAD  SIDE

2

0

2

0

0

0

0

0

 

7

BEAM/SLAB  Bar Shuttering AndConcreting PALAKKAD  SIDE

2

0

2

0

0

0

0

0

 

8

BEAM/SLAB  Staging MOYAN SCHOOL SIDE

4

1

4

0

0

1

0

1

 

9

BEAM/SLAB  Bar bending And Fixing MOYAN SCHOOL SIDE

4

1

4

0

0

0

1

1

 

10

BEAM/SLAB  Shuttering and Concreting MOYAN SCHOOL SIDE

4

1

4

0

0

0

1

1

 

11

BEAM/SLAB RAILWAY SPAN

7

0

7

0

0

0

1

0

 

12

HR/FP/KERB CALICUT  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

13

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

14

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: Progress review done based on the revised Program (rev-01)

 

Availability of Men

 

 

 

 

 

Date

12-03-'11

14-03-'11

15-03-'11

16-03-'11

17-03-'11

18-03-'11

Nof labours

65

65

65

56

56

56

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

 

 

 

Required

Available

Remarks

 

 

 

Fine aggregate {m³}

 

 

 

 

 

 

Cement(bag)

100

755

 

 

 

 

Steel inT

12

95

 

 

 

 

Coarse Aggreagate (m3)

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

 

Utilities to be shifted

 

Remarks

 

 

 

 

BSNL

 

 

 

 

 

 

KSEB

Done

 

 

 

 

 

KWA

Progress

 

 

 

 

 

Others

 

 

 

 

 

 

 

 

 

 

 

 

 
Back
 
    
SHUTTERING FOR RETAINING WALL (18.03.2011)

    
    
BARBENDING OF GIRDER P5 & P6 (18.03.2011)

    
    
BARBENDING FOR RETAINING WALL (18.03.2011)

    
    
STAGING FOR BOWSTRING(17.03.2011)

    
 
    
STAGING FOR BOWSTRING(17.03.2011)

    
    
DESHUTTERING OF RETAINING WALL (17.03.2011)

    
    
BOWSTRING STAGING (17.03.2011)

    
 
    
EXCAVATION FOR RETAINING WALL NEAR P8 (16.03.2011)

    
    
CASTING OF RETAINING WALL (16.03.2011)

    
    
BAR BENDING FOR GIRDER P5 & P6 (16.03.2011)

    
 
    
BAR BENDING FOR GIRDER P5 & P6 (16.03.2011)

    
    
SHUTTERING WORKS OF RETAINING WALL (15.03.2011)

    
    
STAGING FOR GIDER P5 & P6 (15.03.2011)

    
 
 
 

 

 

 

 

 

 

 

Untitled Document