   Weekly report as on 18.03.2011
    
Progress Report For Payyannur ROB for the week ending on 18-03-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE THRIKKARIPUR  SIDE 33 33 0 0 0 0 0 0  
2 PILE EZHIMALA SIDE 27 27 0 0 0 0 0 0  
3 PILE PAYYANNUR SIDE 27 27 0 0 0 0 0 0  
4 PILE CAP THRIKKARIPUR  SIDE 11 11 0 0 0 0 0 0  
5 PILE CAP EZHIMALA SIDE 9 9 0 0 0 0 0 0  
6 PILE CAP PAYYANNUR SIDE 9 9 0 0 0 0 0 0  
9 PIER THRIKKARIPUR  SIDE 11 10 1 0 1 0.5 0.5 0.5  
8 PIER EZHIMALA SIDE 9 5 4 3 3 4 0 0  
9 PIER PAYYANNUR SIDE 9 9 0 0 0 0 0 0  
10 PIER CAP THRIKKARIPUR  SIDE 11 8 3 2 2 0 0 3  
11 PIER CAP EZHIMALA SIDE 9 3 6 4 4 0 6 4  
12 PIER CAP PAYYANNUR SIDE 9 2 7 7 5 2 7 5  
13 RE/R WALL THRIKKARIPUR  SIDE 100% 35% 65% 0 0.00% 0.00% 0.00% 0.00%  
14 RE/R WALL EZHIMALA SIDE 100% 10% 90% 0 0.00% 15.00% 0.00% 0.00%  
15 RE/R WALL PAYYANNUR SIDE 100% 0 100% 6 0.00% 0.00% 100.00% 0.00%  
16 BEAM/SLAB THRIKKARIPUR  SIDE 10 0 10 0 0 0 0 0  
17 BEAM/SLAB EZHIMALA SIDE 8 0 8 0 0 0 0 0  
18 BEAM/SLAB PAYYANNUR SIDE 9 0 9 0 0 0 0 0  
19 HR/FP/KERB THRIKKARIPUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
20 HR/FP/KERB EZHIMALA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
21 HR/FP/KERB PAYYANNUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

Availbility of Men               
Date   3/12/2011 13-03-11 14-03-11 15-03-11 16-03-11 17-03-11 18-03-11
Nof labours   52 52 52 52 60 60 60
                 
Material Stocking Status            
  Required Available Remarks          
Coarse Aggreagate (m3)                
Fine Aggreagate(m3)                
Cement(bag) 200 1200            
Steel(MT) 10 280            

 

 
Back
 
    
P17_P18 SLAB SHUTTERING WITH TOWER CRANE

    
    
P3_P4 SLAB SHUTTERING

    
    
P1_P2 GIRDER SHUTTERING

    
    
EZHIMALA SIDE P15 P16 AP2

    
 
    
BM PART 2

    
    
BM PART 1

      
 

 

 

 

 

 

 

 