Revised Progress Report For Mulankunnathukavu ROB for the week ending on 18-03-2011 |
|
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
Completed |
|
2 |
PILE M.C SIDE |
36 |
36 |
Completed |
|
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
Completed |
|
4 |
PILE CAP M.C SIDE |
12 |
12 |
Completed |
|
5 |
PIER SHORNUR SIDE |
3 |
3 |
Completed |
|
6 |
PIER M.C SIDE |
12 |
12 |
Completed |
|
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
Completed |
|
8 |
PIER CAP M.C SIDE |
12 |
12 |
Completed |
pedestal concreting completed 6 locations.P13,P12,P11,P10,P9,AP2 |
9 |
RE/R WALL SHORNUR SIDE |
100% |
9% |
95% |
0 |
15.00% |
1.00% |
30.00% |
15.00% |
earthwork excavation |
10 |
RE/R WALL M.C SIDE |
100% |
12% |
92% |
0 |
10.00% |
4.00% |
3.00% |
7.00% |
casting of panels 180no: completed. |
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
0 |
3 |
0 |
0 |
0 |
0 |
0* |
|
12 |
BEAM/SLAB M.C SIDE |
12 |
1 |
11 |
0 |
1 |
0 |
1 |
2 |
reinforcement works for the beam at AP2-P13 complete;shuttering works for cross beams and slab in progress. STAGING WORKS FOR THE THIRD SPAN TO BE STARTED VERY SOON. |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
14 |
HR/FP/KERB M.C SIDE |
100% |
0 |
100% |
0 |
0.00% |
1.00% |
0.00% |
2.00% |
|
15 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|