   Report as on 18.03.2011
    
Revised Progress Report For Mulankunnathukavu ROB for the week ending on 18-03-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed  
2 PILE M.C SIDE 36 36 Completed  
3 PILE CAP SHORNUR SIDE 3 3 Completed  
4 PILE CAP  M.C SIDE 12 12 Completed  
5 PIER SHORNUR  SIDE 3 3 Completed  
6 PIER M.C SIDE 12 12 Completed  
7 PIER CAP SHORNUR  SIDE 3 3 Completed  
8 PIER CAP M.C SIDE 12 12 Completed pedestal concreting completed 6 locations.P13,P12,P11,P10,P9,AP2
9 RE/R WALL SHORNUR  SIDE 100% 9% 95% 0 15.00% 1.00% 30.00% 15.00% earthwork excavation 
10 RE/R WALL M.C SIDE 100% 12% 92% 0 10.00% 4.00% 3.00% 7.00% casting of panels 180no: completed.
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0*  
12 BEAM/SLAB M.C SIDE 12 1 11 0 1 0 1 2 reinforcement works for the beam at AP2-P13 complete;shuttering works for cross beams and slab in progress.  STAGING WORKS FOR THE THIRD SPAN TO BE STARTED VERY SOON.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 1.00% 0.00% 2.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

 

Availbility of Men             
Date 12-3-'11 13-3-2011 14-3-2011 15-3-2011 16-3-2011 17-3-2011 18-3-2011
No. of labours 27 23 25 30 32 32 32 

 

 

Material Stocking Status        
  Required Available Remarks      
Fine aggregate {cft} 600 750        
Cement(bag) 700 400 stock will be replendished soon.      
Steel inT 12.35 15 sufficient material available at the site      
Coarse Aggreagate (cft) 3000 3800        

 

 

Utility shifting      
Utilities to be shifted   Remarks    
BSNL  hindrance talked to the BSNL in charge of the locality.agreement made to re-route the cable.    
KSEB already shifted      
KWA  hindrance talked to the panchayat office.work to be started soon.    
Others road diversion work    IN PROGRESS.only bitumenous macadum layer is left to be done.{earthwork excavation }for sectioning}started  today All works completed except bituminous macadum    
  The canal deviation work to be commenced soon after clearing of KWA line and BSNL cable.      
 
Back
 
    
STAGING AND SHUTTERING FOR SLAB AP2-P13 - 12.03.2011

    
    
GROUND LEVELING FOR STAGING WORKOF 3RD SPAN - 14.03.2011

    
    
METALLING FOR SERVICE ROAD DIVERSION - 15.03.2011

    
    
REINFORCEMENT WORK AND SHUTTERING FOR SPAN AP2-P13 - 16.03.2011

    
 
    
PANNEL CASTING - 17.03.2011

    
    
SHUTTERING WORK FOR BEAM AND SLAB AT AP2 - P13 - 18.03.2011

      
 

 

 

 

 

 

 

 