Prevoius Weekly Reports

   weekly progres as on 11.3.2011
    

 

Progress Report For Palakkad Sultanpet ROB for the week ending on 11-03-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
  PCC for RAFT MOYAN SIDE 1 0 1 0 0 0 0 1  
2 PCC for RAFT PALAKKAD SCHOOL SIDE 3 2 1 1 1 0 0 0  
4 RAFT PALAKKAD SIDE 1 1 0 0 0 0 0 0  
5 RAFT MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0  
7 PIER PALAKKAD SIDE 1 1 0 0 0 0 0 0  
8 PIER MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0  
10 PIER CAP PALAKKAD SIDE 1 1 0 0 0 0 0 0  
11 PIER CAP MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0  
13 RE/R WALL PALAKKAD  SIDE 100% 40% 60% 0 0.00% 5.00% 0.00% 0.00%  
14 RE/R WALL MOYAN SCHOOL SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 BEAM/SLAB PALAKKAD  SIDE 2 0 2 0 0 0 0 0  
17 BEAM/SLAB MOYAN SCHOOL SIDE 4 0 4 0 0 0 1 0  
18 BEAM/SLAB RAILWAY SPAN 7 0 7 0 0 0 1 0  
19 HR/FP/KERB CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
20 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
21 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
                     
  Note: Progress review done based on the revised Program (rev-01)      
                     
                     
  Availbility of Men                   
  Date 05-03-'11 07-03-'11 08-03-'11 09-03-'11 10-03-'11 11-03-'11      
  Nof labours 65 65 68 71 68 71      
                     
  Material Stocking Status                  
    Required Available Remarks            
  Fine aggregate {m³}                  
  Cement(bag)   1100              
  Steel inT   115              
  Coarse Aggreagate (m3)                  
                     
  Utility shifting                  
  Utilities to be shifted   Remarks              
  BSNL                  
  KSEB Done                
  KWA                  
  Others                  
                     
 
Back
 
    
CASTING OF DECK SLAB RP7 & P5(12.03.2011)

    
    
RETAINING WALL DESHUTTERING (11.03.2011)

    
    
PIER P5,P6,P7 (11.03.2011)

    
    
BOWSTRING STAGING (11.03.2011)

    
 
    
BOWSTRING STAGING (11.03.2011)

    
    
BAR BENDING WORKS OF DECK SLAB (11.03.2011)

      
 

 

 

 

 

 

 

 