SlNo |
Activity -Description |
Total Quantity |
Cumulative progress up to this week(1) |
Balance work(2) |
Cumulative delay in weeks afterSpplagmnt (3) |
Work planned during the week(4) |
Actual work done during the last week(5) |
Short fall in the last week (6) |
Work Planned for next week (7) |
Remarks |
1 |
Re wall towards NH side |
100% |
15% |
85 |
21 |
0 |
0 |
0 |
5 |
|
2 |
RE wall towards Pulikkakadavuside |
100% |
100 |
0 |
41 |
0 |
0 |
0 |
0 |
|
3 |
Approachspan |
5 No |
4 |
1 |
30 |
- |
- |
- |
- |
|
4 |
Railwayspan |
3No |
0 |
0 |
26 |
|
|
|
|
|
5 |
Pile (Rly)pulikakadavu side |
9 |
4 |
5 |
47 |
0 |
0 |
0 |
0 |
Caution still not available for piling work progress |
6 |
Pile (Rly)Nh side |
9 |
4 |
5 |
|
1 |
1 |
0 |
1 |
Signal cable not removed. |
6 |
Piers (Rly) |
4No |
0 |
0 |
37 |
|
|
|
|
Pier 1stlift at the location P2 ready for concrete. |
7 |
Hand rail (in the pulikkakadavu side) |
426m |
426 |
0 |
|
10 |
10 |
0 |
0 |
|
8 |
Kerb |
639m |
639 |
10 |
- |
10 |
10 |
0 |
0 |
|