   weekly progress 11.3.2011
    

 

SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week(1)  Balance  work(2) Cumulative delay in weeks afterSpplagmnt (3) Work  planned  during the week(4) Actual work done during the last week(5) Short fall in the last week (6) Work  Planned for next week (7) Remarks 
1 Re wall towards NH side  100% 15% 85 21 0 0 0 5   
2 RE wall towards Pulikkakadavuside  100% 100 0 41 0 0 0 0   
3 Approachspan 5 No  4 1 30   
4 Railwayspan 3No  0 0 26               
5 Pile (Rly)pulikakadavu side  9 4 5 47  0  0   0    0   Caution still not available for piling work progress 
6 Pile (Rly)Nh side 9 4 5   1 1 0 1 Signal cable not removed.
6 Piers (Rly)  4No  0 0 37             Pier 1stlift at the location P2 ready for concrete.
7 Hand rail (in the pulikkakadavu side)  426m  426 0     10  10 0  0   
8 Kerb  639m  639 10 10 10 0  0    

 

Material Stocking Status

 Required

Available 

 

Coarse Aggreagate(m3)

10

20

Remarks

Fine Aggreagate(m3)

 4

 6

 

Cement(bag)

 25

 30

 

Steel(MT)

 1.50

 1

 

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 obstruction at the NH side.

 

 

 

KWA

 

 

 

 

Others

 asianetcable at the approachportion.

 

 

  

 

Date 5.3.2011 6.3.2011 7.3.2011 8.3.2011 9.3.2011 10.3.2011
Total No of Labours 30 35 30 30 30 35 
 
Back
 
    
EXCAVTION AT P7 IN THE NH SIDE 10.3.2011

    
    
EXCAVTION AT P7 IN THE NH SIDE 8.3.2011

    
    
RE WALL WORK IN THE NH SIDE 8.3.2011

    
    
RE WALL WORK IN THE NH SIDE 5.3.2011

    
 
    
PILE CONCRETING IN THE NH SIDE 5.3.2011

    
    
PILE CHIPPING IN THE NH SIDE5.3.2011

    
    
PIER SCAFOLDING AT P2 IN PULIKAKADAVU SIDE 9.3.2011

    
 
 
 

 

 

 

 

 

 

 