   Weekly report as on 11.03.2011
    

 

Progress Report For Mulankunnathukavu ROB for the week ending on 11-03-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed  
2 PILE M.C SIDE 36 36 Completed  
3 PILE CAP SHORNUR SIDE 3 3 Completed  
4 PILE CAP  M.C SIDE 12 12 Completed  
5 PIER SHORNUR  SIDE 3 3 Completed  
6 PIER M.C SIDE 12 12 Completed  
7 PIER CAP SHORNUR  SIDE 3 3 Completed pedestal concreting
8 PIER CAP M.C SIDE 12 12 Completed pedestal concreting completed 6 locations.P13,P12,P11,P10,P9,AP2
9 RE/R WALL SHORNUR  SIDE 100% 0 96% 0 10.00% 1.00% 20.00% 15.00% earthwork excavation 
10 RE/R WALL M.C SIDE 100% 1 95% 0 5.00% 3.00% 3.00% 10.00% casting of panels 165no: completed.
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0*  
12 BEAM/SLAB M.C SIDE 12 0 12 0 1 0 1 2 deshuttering of the sides of the girders of the span P11-P12 and the cross beams;staging and bottom shutter setting of the span  AP2 -P13 in progress
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 Utility shifting     Completed   

 

 

Availbility of Men                 
Date 5-3-'11 06-3-'11 07-3-'11 8-3-'11 9/3/2011   10-3-2-'11 11/3/2011
Nof labours 25 1 25 25 25   27 27 

 

Material Stocking Status            
  Required Available Remarks      
Fine aggregate {cft} 600 800        
Cement(bag) 700 100 stock will be replendished soon.      
Steel inT 12.35 21 sufficient material available at the site      
Coarse Aggreagate (cft) 2000 2300        

 

 

Utility shifting              
Utilities to be shifted   Remarks          
BSNL no hindrance            
KSEB already shifted            
KWA no hindrance            
Others road diversion work{earthwork excavation }for sectioning}started  today "36mm" metal loaded at the site.road work to be started very soon.          
  no hindrance from marble shop              
 
Back
 
    
SLAB CONCRETING - 05.03.2011

    
    
AP1 SIDE CONCRETING - 07.03.2011

    
    
PANAL CASTING - 08.03.2011

    
    
DESHUTTERING OF SLAB - 09.03.2011

    
 
    
METAL SUPPLIED FOR SERVICE ROAD - 10.03.2011

    
    
SHUTTERING FOR BEAM AND SLAB - 11.03.2011

      
 

 

 

 

 

 

 

 