Weekly Progress Report - 30.11.2020 to 05.12.2020 |
30.11.2020 |
01.12.2020 |
02.12.2020 |
03.12.2020 |
04.12.2020 |
05.12.2020 |
Machine room and OHT ladder work. |
Electrical cable tray work at duct.
|
Aluminum door frame fixing.
|
Fire PA box fixing work.
|
External painting at east side.
|
Excavation works for external plumbing work.
|
HVAC work. |
.Plumbing work at terrace floor.
|
Fire work at duct. |
SS handrail work at fire stair. |
Aluminum fixed window works. |
SS handrail work at fifth floor fire stair |
Aluminum door work |
. SS handrail work at Sixth floor fire stair
|
SS handrail work at Sixth floor fire stair |
Electrical cable works . |
SS handrail work at fifth floor fire stair. |
Aluminum door frame works. |
Electrical switch fixing and tray work |
Aluminum door work |
HVAC works. |
HVAC works. |
HVAC works. |
HVAC works. and Electrical work. |
External painting at east side |
External painting at east side. |
External painting at east side and internal patch works |
External painting at east side and internal patch works |
Electrical cable works . |
External painting work at East side. |