   Weekly Progress Report - 23.11.2020 to 28.11.2020
    
Weekly Progress Report - 23.11.2020 to 28.11.2020
23.11.2020 24.11.2020 25.11.2020 26.11.2020 27.11.2020 28.11.2020
BC work BC work BC work
BC work
BC work BC work
Drain work Drain work Drain work Drain work Drain work
Drain work
Painting Work Painting Work Painting Work Painting Work Painting Work
Painting Work
Plumbing work Plumbing work       Plumbing work
           
 
Back
 
    
BC LAYING WORK AT RHS SIDE

    
    
WALL CONCRETING COMPLETED AT SLIP ROAD

    
    
CLEANING WORKS FOR BC WORKS AT LHS AND RHS AROOR SIDE

    
    
PLUMBING WORK AT P7-P8

    
 
    
SHUTTERING WORKS FOR WALL CONCRETING AT SLIP ROAD (CROWN PLAZA SIDE)

    
    
PRMER COATING WORKS AT MEDIAN

      
 

 

 

 

 

 

 

 