Weekly Progress Report - 23.11.2020 to 28.11.2020 |
23.11.2020 |
24.11.2020 |
25.11.2020 |
26.11.2020 |
27.11.2020 |
28.11.2020 |
Reinforcment
work of girder-3 at P7-A2 |
Profile work of girder-3 at P7-A2 |
Concrete for A1 dIaphragm first lift |
Shuttering
work of girder-3 at P7-A2 |
Shuttering
work of girder-3 at P7-A2 |
Concrete for Girder-3 at P7-A2 |
Reinforcment work of centre span&Girder-2 @P3-P4 |
Reinforcment work of centre span&Girder-2 @P3-P4 |
Reinforcment work of centre span |
Reinforcment work of centre span |
Reinforcment work of centre span |
Reinforcment work of centre span |
Launching arrangement at P1-P2 location. |
Launching arrangement at P1-P2 location. |
Launching arrangement at P1-P2 location. |
Reinforcement work and shutter maintanence work at yard for center span |
Reinforcement work and shutter maintanence work at yard for center span |
Reinforcement
work of Diaphragm A1 |
Reinforcement work and shutter maintanence work at yard for center span. |
Shuttering work of Diaphragm A1 |
Reinforcement work and shutter maintanence work at yard for center span |
Launching arrangement at P1-P2 location. |
Launching arrangement at P1-P2 location. |
Reinforcement work and shutter maintanence work at yard for center span |
|
Reinforcement work and shutter maintanence work at yard for center span. |
Shuttering
work of girder-3 at P7-A2 |
Reinforcement
work of Diaphragm A1 |
|
|