Weekly Progress Report - 23.11.2020 to 28.11.2020 |
23.11.2020 |
24.11.2020 |
25.11.2020 |
26.11.2020 |
27.11.2020 |
28.11.2020 |
HVAC duct installation work.
|
HVAC duct installation work.
|
HVAC duct installation work. |
HVAC duct installation work. |
HVAC duct installation work. |
Machine room and OHT ladder work. |
External painting at East side., Interior painting |
External painting at East side., Interior painting |
External painting at East side., Interior painting |
External painting at East side., Interior painting |
External painting at East side., Interior painting |
Aluminum door work |
Plumbing work at terrace, Ventilation work |
Plumbing work at terrace, Ventilation work |
Plumbing work at terrace, Ventilation work |
Plumbing work at terrace, Ventilation work |
Plumbing work at terrace, Ventilation work |
HVAC work. |
.Aluminum door work |
Aluminum door work |
Aluminum door work |
Aluminum door work |
Aluminum door work |
Electrical switch fixing and tray work |
Electrical switch fixing,
ELV cable tray work |
Electrical switch fixing,
ELV cable tray work |
Electrical switch fixing,
ELV cable tray work |
Electrical switch fixing,
ELV cable tray work |
Electrical switch fixing,
ELV cable tray work |
External painting at east side |