Weekly Progress Report - 16.11.2020 to 21.11.2020 |
16.11.2020 |
17.11.2020 |
18.11.2020 |
19.11.2020 |
20.11.2020 |
21.11.2020 |
Form-work preparation /installation for slab at 0.00m level at Zone A. (Academic Building) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Building) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Building) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Building) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Building) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Building) |
Cutting and bending of reinforcement for the slab,beams and columns. (Academic Building) |
Shuttering Works/ Reinforcement installation for Columns at Zone B. (Academic Building) |
Cutting and bending of reinforcement for the slab,beams and columns. (Academic Building) |
Cutting and bending of reinforcement for the slab,beams and columns. (Academic Building) |
Cutting and bending of reinforcement for the slab,beams and columns. (Academic Building) |
Cutting and bending of reinforcement for the slab,beams and columns. (Academic Building) |
Shuttering Works/ Reinforcement installation for Columns at Zone B. (Academic Building) |
Form-work preparation/ installation for slab (+3.15m Lvl). (Engg. Building) |
Shuttering Works/ Reinforcement installation for Columns at Zone B. (Academic Building) |
Shuttering Works/ Reinforcement installation for Columns at Zone B. (Academic Building) |
Shuttering Works/ Reinforcement installation for Columns at Zone B. (Academic Building) |
Shuttering Works/ Reinforcement installation for Columns at Zone B. (Academic Building) |
Form-work preparation/ installation for slab (+3.15m Lvl). (Engg. Building) |
Shuttering Works / Reinforcement installation for Columns.(Int. Guest House) |
Form-work preparation/ installation for slab (+3.15m Lvl). (Engg. Building) |
Form-work preparation/ installation for slab (+3.15m Lvl). (Engg. Building) |
Form-work preparation/ installation for slab (+3.15m Lvl). (Engg. Building) |
Form-work preparation/ installation for slab (+3.15m Lvl). (Engg. Building) |
Shuttering Works / Reinforcement installation for Columns.(Int. Guest House) |
Concrete Pouring for Columns & Stairs. (Int. Guest House) |
Shuttering Works / Reinforcement installation for Columns.(Int. Guest House) |
Shuttering Works / Reinforcement installation for Columns.(Int. Guest House) |
Shuttering Works / Reinforcement installation for Columns.(Int. Guest House) |
Shuttering Works / Reinforcement installation for Columns.(Int. Guest House) |