Weekly Progress Report - 16.11.2020 to 21.11.2020 |
16.11.2020 |
17.11.2020 |
18.11.2020 |
19.11.2020 |
20.11.2020 |
21.11.2020 |
Launching of girders |
Concrete of girder -1 at P7-A2. |
Deshuttering work of girder-1 at P7-A2 |
Arrangement for launching girders at P1-P2 location. |
Shuttering work of girder-2 at P7-A2 |
Concrete for 15th girder |
Shuttering works for Pedestal in progress on Center span. |
Profile work of girder-2 at P7- A2 |
Profile work of girder-2 at P7-A2 |
Profile work of girder-2 at P7-A2 location. |
Reinforcement work of girder-3 at P7-A2 and girder-2 at P3-P4 |
Reinforcement work of girder-3 at P7-A2 and girder-2 at P3-P4 |
Reinforcement works and shuttering works for girders in progress |
Reinforcement work of girder-3 at P7-A2 |
Reinforcement work at center span and for diaphragm at A1 location
|
Reinforcement work at center span and for diaphragm at A1 location |
Reinforcement work at center span and for diaphragm at A1 location |
Reinforcement work at center span and for diaphragm at A1 location |
|
Concrete of pedestals at P4 and P5 location |
Bottom shutter work for girder-2 at P3-P4 location. |
Reinforcement work of girder-3 at P7-A2 location. |
Launching arrangement at P1-P2 location. |
Launching arrangement at P1-P2 location. |
|
Reinforcement work at yard for center span. |
Arrangement for launching at P1-P2 location |
Reinforcement work at yard for center span and girders |
Reinforcement work and shutter maintanence work at yard for center span. |
Reinforcement work and shutter maintanence work at yard for center span. |