Weekly Progress Report - 09.11.2020 to 14.11.2020 |
09.11.2020 |
10.11.2020 |
11.11.2020 |
12.11.2020 |
13.11.2020 |
14.11.2020 |
Launching of Girders of first span on Thrissur side. |
Launching of Girders of first span on Thrissur side. |
Launching of Girders of first span on Thrissur side. |
Launching of Girders of first span on Thrissur side. |
Launching of Girders of first span on Thrissur side. |
Launching of girders at first span on Thrissur side. |
Shuttering works for girder at 4th span on Thrissur side. |
Shuttering works for girder at 4th span on Thrissur side. |
Shuttering works for girder at 4th span on Thrissur side. |
Shuttering works for girder at 4th span on Thrissur side. |
Shuttering works for girder at 4th span on Thrissur side. |
Concreting of Girder between P3-P4 completed on Thrissur side. |
Arrangements for Pedestal casting on Center span. |
Arrangements for Pedestal casting on Center span. |
Arrangements for Pedestal casting on Center span. |
Arrangements for Pedestal casting on Center span. |
Arrangements for Pedestal casting on Center span. |
Shuttering works for Pedestal in progress on Center span. |
Shuttering works for box girder on Center span. |
Shuttering works for box girder on Center span. |
Shuttering works for box girder on Center span. |
Shuttering works for box girder on Center span. |
Shuttering works for box girder on Center span. |
Reinforcement works and shuttering works for girders in progress on Kuttipuram side. |
Reinforcement works for 2 girders at Last span on Kuttipuram side. |
Reinforcement works for 2 girders at Last span on Kuttipuram side. |
Reinforcement works for 2 girders at Last span on Kuttipuram side. |
Reinforcement works for 2 girders at Last span on Kuttipuram side. |
Reinforcement works for 2 girders at Last span on Kuttipuram side. |
|