Weekly Progress Report - 09.11.2020 to 14.11.2020 |
09.11.2020 |
10.11.2020 |
11.11.2020 |
12.11.2020 |
13.11.2020 |
14.11.2020 |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work completed |
Painting and cleaning works. |
Painting and cleaning works. |
Painting and cleaning works. |
6mm aggregate laying and levelling work at Under passage (P12-P13) for laying paver block. |
Buffing work starts at Electric pole for primer coating. |
Putty work, primer coating and painting work (Yellow colour) progressing at Crash barrier (inside area). |
Putty work, primer coating and painting work (Yellow colour) progressing at Crash barrier (inside area). |
Drain Works - Excavation, Reinforcement, Shuttering and concrete works. |
Drain Works - Excavation, Reinforcement, Shuttering and concrete works. |
Drain Works - Excavation, Reinforcement, Shuttering and concrete works. |
Drain Works - Excavation, Reinforcement, Shuttering and concrete works. |
Kerb stone fixing work will at Aroor side (Embankment area). |
Kerbstone Fixing |
Putty work, primer coating and painting work (Yellow colour) progressing at Crash barrier (inside area). |
Painting Works |
Site clearing, levelling work at A1-P0 & P0-P1 span for laying PCC. |
Paver laying starts at Under passage (P12-P13). |
Plumbing work at P6-P7 span. |
Plumbing Work |
Kerb stone fixing work will at Aroor side (Embankment area). |
Kerb stone fixing work |
Painting Works, Kerb Stone Works and Plumbing Works. |
Painting Works, Kerb Stone Works and Plumbing Works. |
Reinforcement, Wall Shuttering work at Slip road area (Crown plaza side). |
Drain Works - Excavation, Reinforcement, Shuttering and concrete works. |
Plumbing Works |
Plumbing Works |