   Weekly Progress Report - 02.11.2020 to 07.11.2020
    
Weekly Progress Report - 02.11.2020 to 07.11.2020
02.11.2020 03.11.2020 04.11.2020 05.11.2020 06.11.2020 07.11.2020
Form-work preparation/ installation for slab at 0.00m level at Zone A.  (Academic Block) Form-work preparation/ installation for slab at 0.00m level at Zone A.  (Academic Block) Form-work preparation/ installation for slab at 0.00m level at Zone A.  (Academic Block) Form-work preparation/ installation for slab at 0.00m level at Zone A.  (Academic Block) Form-work preparation/ installation for slab at 0.00m level at Zone A.  (Academic Block) Form-work preparation/ installation for slab at 0.00m level at Zone A.  (Academic Block)
Shuttering Works/Reinforcement installation for Columns & lift at Zone B. (Academic Block) Concrete Pouring for Columns at Zone B, Sunken Slab at Zone A. Shuttering Works/Reinforcement installation for Columns & lift at Zone B. (Academic Block) Shuttering Works/Reinforcement installation for Columns & lift at Zone B. (Academic Block) Shuttering Works/Reinforcement installation for Columns & lift at Zone B. (Academic Block) Shuttering Works/Reinforcement installation for Columns & lift at Zone B. (Academic Block)
Form-work preparation /installation for slab (+3.15m Lvl).(Engg Building) Form-work preparation /installation for slab (+3.15m Lvl).(Engg Building) Form-work preparation /installation for slab (+3.15m Lvl).(Engg Building) Form-work preparation /installation for slab (+3.15m Lvl).(Engg Building) Form-work preparation /installation for slab (+3.15m Lvl).(Engg Building) Form-work preparation /installation for slab (+3.15m Lvl).(Engg Building)
Shuttering Works for Stairs.(Int. Guest House ) Shuttering Works for Stairs and Concrete Pouring for Columns.(Int.  Guest House ) Shuttering Works for Stairs.(Int. Guest House ) Shuttering Works for Stairs.(Int. Guest House ) Shuttering Works for Stairs.(Int. Guest House ) Shuttering Works for Stairs.(Int. Guest House )
Campus Rejuvanation Works - Reinforcement Installation for Drain Campus Rejuvanation Works - Reinforcement Installation for Drain Campus Rejuvanation Works - Reinforcement Installation for Drain Campus Rejuvanation Works - Reinforcement Installation for Drain Campus Rejuvanation Works - Reinforcement Installation for Drain Campus Rejuvanation Works - Reinforcement Installation for Drain
 
Back
 
    

    
    
CONCRETE WORK

    
    

    
    

    
 
    
FORMWORK

    
    
SHUTTERING

    
    
REINFORCEMENT WORK

    
 
    
REINFORCEMENT WORK

    
    

    
    
REINFORCEMENT WORK

    
 
    

    
    

      
 

 

 

 

 

 

 

 