   Weekly report as on 04.03.2011
    

 

Project - ROB at Payyannur

Client - RBDCK

Consultant - KITCO

Contractor - GPT

Manager (RBDCK) - Dino Mani Vithayathil

Project Engineer (KITCO) - George Thampi 

 

Progress Report For Payyannur ROB for the week ending on 04-03-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE THRIKKARIPUR  SIDE 33 33 0 0 0 0 0 0  
2 PILE EZHIMALA SIDE 27 27 0 0 0 0 0 0  
3 PILE PAYYANNUR SIDE 27 27 0 0 0 0 0 0  
4 PILE CAP THRIKKARIPUR  SIDE 11 11 0 0 0 0 0 0  
5 PILE CAP EZHIMALA SIDE 9 9 0 0 0 0 0 0  
6 PILE CAP PAYYANNUR SIDE 9 9 0 0 0 0 0 0  
7 PIER THRIKKARIPUR  SIDE 11 8 3 0 1 0.5 1 1  
8 PIER EZHIMALA SIDE 9 4 5 3 3 1 3 3  
9 PIER PAYYANNUR SIDE 9 7.5 1.5 1.5 1.5 1.5 0 0  
10 PIER CAP THRIKKARIPUR  SIDE 11 6 5 1 1 0 2 1  
11 PIER CAP EZHIMALA SIDE 9 0 9 4 4 0 4 4  
12 PIER CAP PAYYANNUR SIDE 9 0 9 9 5 0 9 5  
13 RE/R WALL THRIKKARIPUR  SIDE 100% 35% 65% 0 0.00% 0.00% 0.00% 0.00%  
14 RE/R WALL EZHIMALA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 RE/R WALL PAYYANNUR SIDE 100% 0 100% 6 0.00% 0.00% 100.00% 0.00%  
16 BEAM/SLAB THRIKKARIPUR  SIDE 10 0 10 0 0 0 0 0  
17 BEAM/SLAB EZHIMALA SIDE 8 0 8 0 0 0 0 0  
18 BEAM/SLAB PAYYANNUR SIDE 9 0 9 0 0 0 0 0  
19 HR/FP/KERB THRIKKARIPUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
20 HR/FP/KERB EZHIMALA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
21 HR/FP/KERB PAYYANNUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

Availbility of Men               
Date   26-02-11 27-02-11 28-02-11 1/3/2011 2/3/2011 3/3/2011 4/3/2011
Nof labours   48 52 48 52 48 52 48 

 

Material Stocking Status      
Coarse Aggreagate (m3) Required Available Remarks  
Fine Aggreagate(m3)        
Cement(bag) 200 1100    
Steel(MT) 10 300     
 
Back
 
    
RBDCK MANAGER RDS PM KITCO PE - 04.03.2011

    
    
P17 PIER BEAM SHUTTERING - 04.03.2011

    
    
CURING OF SLAB AP1_P1 - 04.03.2011

    
    
SLAB CONCRETED - 02.03.2011

    
 
    
AP1 P1 SLAB CONCRETING 01.03.2011

    
    
AP1 P1 BEAM CONCRETNG - 26.02.2011

    
    
AP1 P1 BEAM CONCRETING AT NIGHT - 25.02.2011

    
 
 
 

 

 

 

 

 

 

 