Weekly Progress Report - 02.11.2020 to 07.11.2020 |
02.11.2020 |
03.11.2020 |
04.11.2020 |
05.11.2020 |
06.11.2020 |
07.11.2020 |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Painting work progressing at Crash barrier (Outside area) |
Painting work progressing at Crash barrier (Outside area) |
Painting work progressing at Crash barrier (Outside area) |
Grinding work progressing at Crash barrier (inside area). |
Shuttering at pamba steel area and concrete. Excavation at pamba steel area for drain work. |
Grinding, Putty work, primer coating work progressing at Crash barrier (inside area). |
Reinforcement work and Deshuttering at pamba steel area |
Reinforcement work and Shuttering at pamba steel area |
Reinforcement work and Shuttering at pamba steel area and wall concrete. |
Shuttering at pamba steel area. |
Kerb stone fixing work at vyttila side (Embankment area). |
WMM filling and levelling work at Under passage (P12-P13). |
Deshuttering work at aroor side slip road (Le meridian side) |
|
Kerb stone fixing work at vyttila side (Embankment area). |
Kerb stone fixing work at vyttila side (Embankment area). |
Plumbing work starts at P12-P13 (Outer side). |
Drain Works - Excavation, Reinforcement, Shuttering and concrete works. |
|
|
Plumbing work at P13-A2 (Outer side) |
Plumbing work at P12-P13 (Outer side). |
Under passage (P12-P13) work starts. |
Kerbstone and Plumbing Works |