Weekly Progress Report - 26.10.2020 to 31.10.2020 |
26.10.2020 |
27.10.2020 |
28.10.2020 |
29.10.2020 |
30.10.2020 |
31.10.2020 |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Metal Crash Barrier work |
Metal Crash Barrier work |
Metal Crash Barrier work |
Painting work progressing at Crash barrier (Outside area) |
Painting work progressing at Crash barrier (Outside area) |
Painting work progressing at Crash barrier (Outside area). |
Excavation for drain |
Excavation for drain |
Excavation for drain |
Shuttering work starts at pamba steel area. |
Shuttering work starts at pamba steel area. |
Reinforcement work and Shuttering work for drain |
|
Bar bending for drain |
Pcc for drain |
Plumbing work starts at P13-A2 span. |
Deshuttering work and Shuttering works at aroor side slip road (Le meridian side). |
Plumbing work at P13-A2 span. |
|
|
Bar bending for drain |
|
Plumbing work starts at P13-A2 span. |
Metal beam crash barrier work progressing at aroor side (Slip road). |