Weekly Progress Report - 19.10.2020 to 24.10.2020 |
19.10.2020 |
20.10.2020 |
21.10.2020 |
22.10.2020 |
23.10.2020 |
24.10.2020 |
Staging work of center span |
Staging work of center span |
Staging work of center span |
Staging work of center span |
Staging work of center span |
Staging work of center span |
Shuttering work of girder between P2-P3 |
Stressing and grouting of 6 girders completed |
Arrangements for launching of girders at A1-P1 location |
Arrangements for launching of girders at A1-P1 location. |
Arrangements for launching of girders at A1-P1 location. |
Arrangements for launching of girders at A1-P1 location. |
|
Concrete of girderbetween P2-P3 |
|
staging works for girder casting at A2-P7 location |
staging works for girder casting at A2-P7 location |
staging works for girder casting at A2-P7 location |
|
|
|
|
|
|