Weekly Progress Report - 19.10.2020 to 24.10.2020 |
19.10.2020 |
20.10.2020 |
21.10.2020 |
22.10.2020 |
23.10.2020 |
24.10.2020 |
DBM work at Aroor side completed on Sunday. |
Mastic asphalt work. |
Mastic asphalt work affected due to rain. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Kerb stone fixing work |
Kerb stone fixing work |
Drain Reinforcement and Shuttering work |
Drain Raft concreting work near slip road |
Drainage Sppout Plumbing work |
Kerb stone fixing work at A1 retaining wall. (Crown plaza side). |
Reinforcement and shuttering work at pamba steel area. Planning for wall concrete. |
Reinforcement and shuttering work at pamba steel area. Planning for wall concrete. |
Drainage Sppout Plumbing work |
Drainage Sppout Plumbing work |
Painting work |
Reinforcement and shuttering work at pamba steel area. Planning for wall concrete. |
Metal beam crash barrier work at aroor side (Slip road - Le meridian side) |
|
Painting work |
|
|
Metal beam crash barrier work at aroor side (Slip road - Le meridian side) |
|
|
|
|
|