   Weekly Progress Report - 19.10.2020 to 24.10.2020
    
Weekly Progress Report - 19.10.2020 to 24.10.2020
19.10.2020 20.10.2020 21.10.2020 22.10.2020 23.10.2020 24.10.2020
DBM work at Aroor side completed on Sunday. Mastic asphalt work. Mastic asphalt work affected due to rain. Mastic asphalt work. Mastic asphalt work. Mastic asphalt work.
Mastic asphalt work. Kerb stone fixing work Kerb stone fixing work Drain Reinforcement and Shuttering work Drain Raft concreting work near slip road Drainage Sppout Plumbing work
Kerb stone fixing work at A1 retaining wall. (Crown plaza side). Reinforcement and shuttering work at pamba steel area. Planning for wall concrete. Reinforcement and shuttering work at pamba steel area. Planning for wall concrete. Drainage Sppout Plumbing work Drainage Sppout Plumbing work Painting work
Reinforcement and shuttering work at pamba steel area. Planning for wall concrete. Metal beam crash barrier work  at aroor side (Slip road - Le meridian side)   Painting work    
Metal beam crash barrier work  at aroor side (Slip road - Le meridian side)          
 
Back
 
    
DRAIN RAFT CONCRETING WORK

    
    
PLUMBING WORK

    
    
MASTIC ASPHALT WORK

    
    
DRAINAGE WORK

    
 
    
DRAINAGE WORK

    
    
DRAINAGE WORK

    
    
DRAINAGE WORK

    
 
    
KERB WORK

    
    
DBM WORK

      
 

 

 

 

 

 

 

 