Weekly Progress Report - 12.10.2020 to 17.10.2020 |
12.10.2020 |
13.10.2020 |
14.10.2020 |
15.10.2020 |
16.10.2020 |
17.10.2020 |
Reinforcement works of girder between P2-P3 |
Reinforcement works of girder between P2-P3 |
Reinforcement works of girder between P2-P3 |
Shuttering work of girder between P2-P3 |
Shuttering work of girder between P2-P3 |
Shuttering work of girder between P2-P3 |
Staging work of center span |
Staging work of center span |
Shuttering work of girder between P2-P |
Staging work of center span |
Staging work of center span |
Staging work of center span |
|
|
|
|
|
. |
|
|
|
|
|
|