Weekly Progress Report - 12.10.2020 to 17.10.2020 |
12.10.2020 |
13.10.2020 |
14.10.2020 |
15.10.2020 |
16.10.2020 |
17.10.2020 |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Plumbing work starts at P7-P8 span. |
Plumbing work starts at P8-P9 span. |
Plumbing work starts at P8-P9 span. |
Painting work (Off white colour) on outside area of crash barrier. |
Painting work (Off white colour) on outside area of crash barrier. |
Painting work (Red colour) on outside area of crash barrier. |
Kerb stone fixing work at A1 retaining wall area (Le meridian side) |
Kerb stone fixing work starts at A1 retaining wall area (Le meridian side) |
Metal beam crash barrier work at aroor side (Slip road - Le meridian side) |
Metal beam crash barrier work at aroor side |
Metal beam crash barrier work at aroor side |
Metal beam crash barrier work |
Shuttering work for drainage at slip road area. (Aroor side) |
Deshuttering work for drainage at slip road area. (Aroor side). |
Deshuttering work for drainage at slip road area. (Aroor side). |
Plumbing, kerbstone work etc are progressing |
Excavation work progressing at aroor side slip road. (Crown plaza side). |
Deshuttering work for drainage at slip road area at Aroor side (Le meridian side). |
Painting work (Off white colour) on crash barrier (outside side area). |
Shuttering work at pamba steel area. |
Shuttering work for drainage at slip road area. (Aroor side). |
Shuttering work for drainage at slip road area. (Aroor side). |
Plumbing, kerbstone etc are progressing |
Plumbing, kerbstone etc are progressing |