Weekly Progress Report - 05.10.2020 to 10.10.2020 |
05.10.2020 |
06.10.2020 |
07.10.2020 |
08.10.2020 |
09.10.2020 |
10.10.2020 |
Shuttering work of girder -3 between P2-P3 |
Concrete of girder-3 between P2-P3 |
De Shuttering work of girder -3 between P2-P3 |
Staging work of center span |
Staging work of center span |
Staging work of center span |
Staging work of center span |
Staging work of center span |
Staging work of center span |
HT strands cutting and placing |
HT strands cutting and placing |
HT strands cutting and placing |
HT strands cutting and placing |
HT strands cutting and placing |
HT strands cutting and placing |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|