Prevoius Weekly Reports

   Weekly Progress Report - 05.10.2020 to 10.10.2020
    
Weekly Progress Report - 05.10.2020 to 10.10.2020
05.10.2020 06.10.2020 07.10.2020 08.10.2020 09.10.2020 10.10.2020
Fire alarm work. Granite work Granite work Aluminium work at yard. Aluminium work at yard. Aluminium work at yard.
SS handrail work at fire stair. ceiling painting. ceiling painting. Stair side plastering. Stair side plastering. Stair side plastering.
Aluminum fabrication work at yard. Window grill fabrication. Window grill fabrication. Fire safety work. Fire safety work. Fire safety work.
  Aluminum fabrication work at yard. Aluminum fabrication work at yard. SS handrail work. SS handrail work. SS handrail work.
  Fire work at 2nd floor. Fire work at 2nd floor.      
 
Back
 
    
TILE WORK

    
    
GRILL FABRICATION WORK

    
    
GRILL FABRICATION WORK

    
    
HANDRAIL WORK

    
 
    
TILE WORK

    
    
ALUMINUM WORK

    
    
PLASTERING WORK

    
 
    
HANDRAIL WORK

    
    
ALUMINUM WORK

    
    
FIRE SAFETY WORK

    
 
    
GRILL FABRICATION WORK

    
    
GRANITE FLOORING WORK

    
    
ALUMINUM WORK

    
 
    
FIRE SAFETY WORK

    
    
HANDRAIL WORK

    
    
FIRE SAFETY WORK

    
 
    
ALUMINUM WORK

      
 

 

 

 

 

 

 

 