Weekly Progress Report - 28.09.2020 to 03.10.2020 |
28.09.2020 |
29.09.2020 |
30.09.2020 |
01.10.2020 |
02.10.2020 |
03.10.2020 |
Grill fabrication |
Aluminum work. |
Electrical work at 3rd floor |
Window grill work |
Plumbing work at duct |
Tile work at 5th floor. |
Electrical work at 5th floor. |
Grill painting |
Ceiling painting at 4th floor. |
Granite work at 5th floor. |
Aluminum fabrication work. |
Window grill painting. |
Aluminum window fixing. |
|
Window grill painting. |
Window grill painting. |
External painting at West side. |
Aluminum fabrication work at yard. |
HVAC work |
|
Aluminum work. |
Aluminum work. |
Window grill fabrication work. |
Window grill fabrication. 4. |
|
|
Plumbing work at duct. |
|
Fire alarm works. |
|