Weekly Progress Report - 05.10.2020 to 10.10.2020 |
05.10.2020 |
06.10.2020 |
07.10.2020 |
08.10.2020 |
09.10.2020 |
10.10.2020 |
Plumbing work starts at P4-P5 span. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Primer coating work starts at Crash barrier (Outer side) at Crown plaza side.
|
Plumbing work at P4-P5 span.
|
Plumbing work at P4-P5 span.
|
Plumbing work at P7-P8 span |
Plumbing work at P7-P8 span |
Plumbing work |
Shuttering work at Thripunitura road drain and aroor side slip road. Planning for wall concrete. |
Kerb stone fixing work at aroor side (Median) |
Kerb stone fixing at aroor side (Median) |
Kerb stone fixing work starts at A1 retaining wall area (Le meridian side) |
Kerb stone fixing work |
.Kerb stone fixing work |
Kerb stone fixing work at aroor side (Median)
|
Deshuttering work starts at aroor side slip road drain. Reinforcement work for drain starts near pamba steel area. |
Shuttering work progressing at aroor side slip road drain and pamba steel area.
|
Deshuttering work progressing at aroor side slip road drain and pamba steel area |
Shuttering work for drainage |
Shuttering work for drainage |
|
Retaining wall painting (Second coat) starts at vyttila side (Crown plaza side). |
Raft concrete for drain near pamba steel area. |
Planning for reinforcement work at pamba steel area. |
Painting work |
Painting work |