Weekly Progress Report - 28.09.2020 to 03.10.2020 |
28.09.2020 |
29.09.2020 |
30.09.2020 |
01.10.2020 |
02.10.2020 |
03.10.2020 |
Mastic asphalt work.
|
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Mastic asphalt work. |
Plumbing work at P3-P4 span. |
Plumbing work at P3-P4 span.
|
Plumbing work at P3-P4 span.
|
Plumbing work at P3-P4 span.
|
Plumbing work at P3-P4, P4-P5 span.
|
Plumbing work at P4-P5 span.
|
Grinding work on retaining wall at vyttila side(Le meridian side) |
Putty Work & Painting work |
Putty work on retaining wall at vyttila side(Crown plaza side) |
Putty work on retaining wall at aroor side(Le meridian side) |
Primer coating work on retaining wall at vyttila side.
|
Putty work on retaining wall at vyttila side. |
Primer coating work at outside of crash barrier at aroor side(Crown plaza side) |
Deshuttering work (Wall) and reinforcement work progressing at slip road (Aroor side). |
Shuttering work (Wall) and reinforcement work progressing at slip road (Aroor side). |
|
Deshuttering work at aroor side slip road. |
Shuttering work at aroor side slip road. |
Shuttering work and reinforcement work progressing at slip road (Aroor side). Deshuttering work at pamba steel area. |
Excavation work at slip road at aroor side. |
Excavation work at slip road at aroor side |
|
Reinforcement for drainage near pamba steel area. |
Primer coating work at Crash barrier (Outer side) at Crown plaza side |