Weekly Progress Report - 21.09.2020 to 26.09.2020 |
21.09.2020 |
22.09.2020 |
23.09.2020 |
24.09.2020 |
25.09.2020 |
26.09.2020 |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Block) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Block) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Block) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Block) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Block) |
Form-work preparation/ installation for slab at 0.00m level at Zone A. (Academic Block) |
Cutting and bending of reinforcement for the slab,beams and columns |
Cutting and bending of reinforcement for the slab,beams and columns |
Cutting and bending of reinforcement for the slab,beams and columns |
Cutting and bending of reinforcement for the slab,beams and columns |
Cutting and bending of reinforcement for the slab,beams and columns |
Cutting and bending of reinforcement for the slab,beams and columns |
Solid block Masonry for Plinth walls at Zone B.(Academic Block) |
Solid block Masonry for Plinth walls at Zone B.(Academic Block) |
Solid block Masonry for Plinth walls at Zone B.(Academic Block) |
Shuttering works for Retaining wall at Grid F. (Academic Block) |
Shuttering works for columns. (Int. Guest House ) |
Shuttering works for columns. (Int. Guest House ) |
Soil Backfilling inside Plinth Wall at Zone B.(Academic Block) |
Soil Backfilling inside Plinth Wall at Zone B.(Academic Block) |
Soil Backfilling inside Plinth Wall at Zone B.(Academic Block) |
Rebar installation for columns.(Int. Guest House ) |
Plastering works and Solid Block Masonry for Plinth walls. (Engg Block ) |
Plastering works and Solid Block Masonry for Plinth walls. (Engg Block ) |
|
|
|
Plastering works and Solid Block Masonry for Plinth walls. (Engg Block ) |
|
|