   Weekly Progress Report - 21.09.2020 to 26.09.2020
    
Weekly Progress Report - 21.09.2020 to 26.09.2020
21.09.2020 22.09.2020 23.09.2020 24.09.2020 25.09.2020 26.09.2020
Painting work
Plumbing work at P2-P3 span
Drainage reinforcement work and Excavation on slip road at aroor side(Le meridian side).
Drain shuttering work at pamba steel area.
Drain shuttering work at pamba steel area.
Drain reinforcement and shuttering work at slip road. Wall concreting at pamba steel area. 
Reinforcement bar bending for drain 
PCC work on drain at A2 side (Le meridian side) Plumbing work at P2-P3 span. Plumbing work  at P2-P3 span. Plumbing work  at P2-P3 span.
Plumbing work at P2-P3 span.
Plumbing work at  P11-P12 pier cap works delayed due to rain.  Grinding work on retaining wall at aroor side(Le meridian side). Drain Cover slab laying at Thripunithura side Grinding work  on retaining wall at aroor side(Crown plaza side). Grinding work on retaining wall at vyttila side(Le meridian side).
works delayed due to rain.          Drain PCC work at thripunitura road
           
 
Back
 
    
PUTTY WORK

    
    
PLUMBING WORK

    
    
DRAIN WORK

    
    
DRAIN WORK

    
 
    
CONCRETE WORK

    
    
DRAIN WORK

    
    
DRAIN WORK

    
 
    
PLUMBING WORK

    
    
DE SHUTTERING WORK

    
    
DRAIN WORK

    
 
    
EXCAVATION WORK

    
    
PLUMBING WORK

    
    
DRAIN WORK

    
 
    
PCC FOR DRAIN

    
    
PLUMBING WORK

      
 

 

 

 

 

 

 

 