Weekly Progress Report - 21.09.2020 to 26.09.2020 |
21.09.2020 |
22.09.2020 |
23.09.2020 |
24.09.2020 |
25.09.2020 |
26.09.2020 |
Painting work
|
Plumbing work at P2-P3 span |
Drainage reinforcement work and Excavation on slip road at aroor side(Le meridian side).
|
Drain shuttering work at pamba steel area.
|
Drain shuttering work at pamba steel area. |
Drain reinforcement and shuttering work at slip road. Wall concreting at pamba steel area.
|
Reinforcement bar bending for drain
|
PCC work on drain at A2 side (Le meridian side) |
Plumbing work at P2-P3 span. |
Plumbing work at P2-P3 span. |
Plumbing work at P2-P3 span. |
Plumbing work at P2-P3 span.
|
Plumbing work at P11-P12 pier cap |
works delayed due to rain. |
Grinding work on retaining wall at aroor side(Le meridian side). |
Drain Cover slab laying at Thripunithura side |
Grinding work on retaining wall at aroor side(Crown plaza side). |
Grinding work on retaining wall at vyttila side(Le meridian side). |
works delayed due to rain. |
|
|
|
|
Drain PCC work at thripunitura road |
|
|
|
|
|
|