Weekly Progress Report - 14.09.2020 to 19.09.2020 |
14.09.2020 |
15.09.2020 |
16.09.2020 |
17.09.2020 |
18.09.2020 |
19.09.2020 |
Concrete Pouring for Columns (First lift) U.G.F - G.F,Zone A |
Form-work preparation/ installation for slab at -2.70m level at Zone A.
|
Form-work preparation/ installation for slab at -2.70m level at Zone A. |
Form-work preparation/ installation for slab at -2.70m level at Zone A. |
Form-work preparation/ installation for slab at -2.70m level at Zone A. |
Form-work preparation/ installation for slab at -2.70m level at Zone A. |
Beam Reinforcement installation for Slab at -2.70m level, Zone A |
Solid block Masonry for Plinth walls at Zone B |
Solid block Masonry for Plinth walls at Zone B. |
Soil Backfilling inside Plinth Wall at Zone B.
|
Solid block Masonry for Plinth walls at Zone B.
|
Solid block Masonry for Plinth walls at Zone B. |
Staircase Concreting -2.7 TO -1.35 Zone - A ; Lift Pit-3 Concreting in Zone-A (-1.60 TO -0.5 ) |
Soil Backfilling inside Plinth Wall at Zone B. |
Soil Backfilling inside Plinth Wall at Zone B. |
Cutting and bending of reinforcement for the slab,beams and columns.
|
Soil Backfilling inside Plinth Wall at Zone B.
|
Soil Backfilling inside Plinth Wall at Zone B. |
Concrete Pouring for Columns (First lift) G.F-F.F @ International Guest House. |
Cutting and bending of reinforcement for the slab,beams and columns. |
Cutting and bending of reinforcement for the slab,beams and columns. |
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
|
|
|
|
|
|