Weekly Progress Report - 07.09.2020 to 12.09.2020 |
07.09.2020 |
08.09.2020 |
09.09.2020 |
10.09.2020 |
11.09.2020 |
12.09.2020 |
Shuttering works for Girder between P2_P3 in progress. |
Shuttering works for Girder between P2_P3 in progress. |
Concreting of first Girder between P2-P3 |
Shuttering work for girder-3 between A2-P7 |
Shuttering work for girder-3 between A2-P7 |
Reinforcement works for second girder at P2-P3 |
Reinforcement works in progress at yard. |
Reinforcement works |
Cable profiling works at P7-A2 , 3rd Girder |
Deshuttering work for girder-1 between P2-P3 |
Deshuttering work for girder-1 between P2-P3 |
Bottom Shuttering works at P2-P3locatiin. |
Work is disrupting due to heavy rain. |
|
|
|
|
Shuttering works for Third girder at P7-A2 location. |
|
|
|
|
|
|
|
|
|
|
|
|