Weekly Progress Report - 07.09.2020 to 12.09.2020 |
07.09.2020 |
08.09.2020 |
09.09.2020 |
10.09.2020 |
11.09.2020 |
12.09.2020 |
Putty work on crash barrier outside side (Le meridian side). |
Primer coating work starts on P12-P13 span. |
Putty work starts on outside crash barrier (Le meridian side). |
Primer coating work starts on P13-A2 span. |
Primer coating and putty work on P12-P13 span. |
Kerb stone fixing work starts on P11-P12 span |
Landscape work at aroor side (Crown plaza side). |
Landscape work starts at aroor side (Le meridian side side). |
Landscape work starts at aroor side (Le meridian side side). |
There is no work in embankment area. |
Rectification work - Cutting of existing steel, Filling work, etc. |
Painting work at A2 abutment side |
Kerb stone fixing work at Median side (Vyttila embankment side).
|
Kerb stone fixing work starts at Median side (Vyttila embankment side). |
Shuttering work for drain wall progressing near pamba steel. |
Shuttering work for drain wall progressing near pamba steel. Planning for concreting. |
Kerb stone fixing work |
Works are delaying due to rain |
Metal beam crash barrier work progressing at aroor side (Crown plaza side) |
Cleaning work (above existing Road) progressing for road work at aroor side (Le meridian side) |
Cleaning work (above existing Road) progressing for road work at aroor side (Le meridian side) |
Works are delaying due to rain |
Works are delaying due to rain |
|
|
Works are delaying due to rain |
Works are delaying due to rain |
|
|
|