Weekly Progress Report - 07.09.2020 to 12.09.2020 |
07.09.2020 |
08.09.2020 |
09.09.2020 |
10.09.2020 |
11.09.2020 |
12.09.2020 |
Shuttering work for stairs and Lift pit-3 at Zone A. |
Form-work preparation/installation for slab at -2.70m level at Zone A. |
Form-work preparation/installation for slab at -2.70m level at Zone A. |
Form-work preparation/installation for slab at -2.70m level at Zone A. |
No major Site Activities are carried out today due to rain. |
No major Site Activities are carried out today due to rain. |
Soil Backfilling inside the Plinth wall at Zone B.
|
Soil Backfilling inside Plinth Wall at Zone B.
|
Shuttering work for Lift pit-3 & Stair Case at Zone A.
|
Shuttering work for Lift pit-3 at Zone A.
|
|
|
Plastering work for Plinth walls at Zone B.
|
Plastering works for Plinth walls at Zone B.
|
Plastering work for Plinth walls at Zone B.
|
Cutting and bending of reinforcement for the slab,beams and columns. |
|
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
Soil Backfilling inside Plinth at Zone B.
|
|
|
|
|
|
Cutting and bending of reinforcement for the slab,beams and columns.
|
|
|
|