Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886329
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report - 07.09.2020 to 12.09.2020
    
Weekly Progress Report - 07.09.2020 to 12.09.2020
07.09.2020 08.09.2020 09.09.2020 10.09.2020 11.09.2020 12.09.2020
Shuttering work for stairs and Lift pit-3 at Zone A. Form-work preparation/installation for slab at -2.70m level at Zone A.  Form-work preparation/installation for slab at -2.70m level at Zone A.  Form-work preparation/installation for slab at -2.70m level at Zone A.  No major Site Activities are carried out today due to rain. No major Site Activities are carried out today due to rain.

Soil Backfilling inside the Plinth wall at Zone B.
Soil Backfilling inside Plinth Wall at Zone B.
Shuttering work for Lift pit-3 & Stair Case at Zone A.
Shuttering work for Lift pit-3 at Zone A.
   
Plastering work for Plinth walls at Zone B.
Plastering works for Plinth walls at Zone B.
Plastering work for Plinth walls at Zone B.
Cutting and bending of reinforcement for the slab,beams and columns.    
Cutting and bending of reinforcement for the slab,beams and columns.
Cutting and bending of reinforcement for the slab,beams and columns.
Soil Backfilling inside Plinth at Zone B.
     
   
Cutting and bending of reinforcement for the slab,beams and columns.
     
 
Back
 
    
SHUTTERING WORK FOR COLUMN

    
    
SHUTTERING WORK FOR LIFT

    
    
REINFORCEMENT BENDING & CUTTING

    
    
FORMWORK INSTALLATION WORK

    
 
    
SOIL FILLING FOR PLINTH

    
    
PLASTERING WORK

    
    
SOIL COMPACTION

    
 
    
PLASTERING WORK

    
    
REINFORCEMENT WORK FOR STAIR

    
    
PLASTERING WORK

    
 
    
REINFORCEMENT BENDING & CUTTING

    
    
REINFORCEMENT WORK

      
 

 

 

 

 

 

 

 

Untitled Document