Weekly Progress Report - 07.09.2020 to 12.09.2020 |
07.09.2020 |
08.09.2020 |
09.09.2020 |
10.09.2020 |
11.09.2020 |
12.09.2020 |
Sunken filling at 3rd floor gents toilet. |
Aluminum fabrication work at yard. |
Granite flooring at fire stair 4th floor |
Granite flooring at fire stair 4th floor |
Granite flooring at fire stair 3rd floor
|
Aluminum fabrication work at yard. |
Grill works.
|
Grill works at yard. |
Plumbing work at Duct K7
|
Electrical work at 4th floor
|
Electrical work at 2nd floor
|
Fire stair granite laying at first floor.
|
Aluminum fabrication works.
|
Electrical work at 4th floor |
Aluminum fabrication work at yard. |
Aluminum fabrication work at yard.
|
Aluminum fabrication and Grill workswork at yard
|
Grill works at yard
|
|
|
Grill works at yard. |
Grill works at yard.
|
Plumbing work at K7 duct |
|
|
|
Electrical work at 4th floor |
|
Transformer platform concrete.
|
|